Sheet 1: RAP 3 RKB
RENCANA ANGGARAN PELAKSANAAN (RAP)










KEGIATAN PEMBANGUNAN 3 RUANG KELAS BARU





PEKERJAAN PEMBANGUNAN 3 RUANG KELAS BARU





LOKASI GEDUNG SMA ISLAM SULTAN FATAH WEDUNG DEMAK





SUMBER DANA APBN





TAHUN ANGGARAN 2012










No JENIS PEKERJAAN VOLUME Harga Satuan (Rp) Jumlah (Rp) Total (Rp)
1 2 3 4 5 6
1




-






-






-






-






-







-
2 Pek. Slof, Kolom Balok, Lt






1 Pasir 6.00 rit 1,250,000.00 7,500,000.00

2 Kris 3.00 rit 1,450,000.00 4,350,000.00

3 Cement (40 kg) 195.00 zak 50,000.00 9,750,000.00

4 Papan 20 x 20 x 2 cm 300.00 lbr 7,000.00 2,100,000.00

5 Bambu Pancang Ø 10 - 13 cm 50.00 btg 35,000.00 1,750,000.00







25,450,000.00
3 Pek. Pasang Batu Bata + Plaster + Aci






1 Batu Bata 28,000.00 bh 500.00 14,000,000.00

2 Pasir 6.00 rit 1,250,000.00 7,500,000.00

3 Cement (40 kg) 150.00 zak 50,000.00 7,500,000.00







29,000,000.00
4 Pek. Kolong, Slop, Ring Balok, Kuda-kuda






1 Besi Ø 6 270.00 btg 22,000.00 5,940,000.00

2 Besi Ø 10 175.00 btg 86,000.00 15,050,000.00

3 Besi Ø 12 172.00 btg 107,000.00 18,404,000.00

4 Bendrat 3.00 rol 360,000.00 1,080,000.00







34,534,000.00
5 Pek. Plat






1 Cement (40 kg) 300.00 zak 50,000.00 15,000,000.00

2 Pasir 5.00 rit 1,250,000.00 6,250,000.00

3 Kris 4.00 rit 1,450,000.00 5,800,000.00







27,050,000.00
6 Pek. Steger/Perancah
1.00 ls 22,500,000.00 22,500,000.00

1 Triplek 80.00 lbr 105,000.00 8,400,000.00

2 Genteng 7,500.00 bh 1,125.00 8,437,500.00







39,337,500.00
7 Pek. Plafond 300 m²



-

1 Kayu Glugu 4/6 x 4 m 150.00 btg 26,000.00 3,900,000.00

2 Eternit 100 x 100 300.00 15,250.00 4,575,000.00

3 Pek. Listplang Board 107.00 15,000.00 1,605,000.00







10,080,000.00
8




- -
9 Pek. Cat-catan
3.00 ls 4,000,000.00 12,000,000.00 12,000,000.00
10 Pek. Lantai 3 RKB



-

1 Keramik 30 x 30 290.00 50,000.00 14,500,000.00

2 Pasir 2.00 rit 1,250,000.00 2,500,000.00

3 Cement (40 kg) 50.00 zak 50,000.00 2,500,000.00







19,500,000.00
11 Upah Tenaga 23% dari Jml Pekerjaan Seluruhnya
1.00 ls 48,000,000.00 48,000,000.00 48,000,000.00
12 Pek. Kusen Pintu dan Jendela
3.00 ls 7,500,000.00 22,500,000.00 22,500,000.00
13 Mebelair

RKB
- -
14 Biaya administrasi + Laporan (DO) 5%
1.00 ls 8,862,817.50 8,862,817.50 8,862,817.50
Jumlah
276,314,317.50













Wedung, 11 Februari 2013











Ketua Pelaksana

Bendahara Pelaksana



























BUDIYONO, ST

MAHMUDI, S.Pd.I


Sheet 2: LAB IPA
RENCANA ANGGARAN PELAKSANAAN (RAP)










KEGIATAN LAB IPA





PEKERJAAN LAB IPA





LOKASI GEDUNG SMA ISLAM SULTAN FATAH WEDUNG DEMAK





SUMBER DANA APBN





TAHUN ANGGARAN 2012










No JENIS PEKERJAAN VOLUME Harga Satuan (Rp) Jumlah (Rp) Total (Rp)
1 2 3 4 5 6
1 Pek. Pondasi






1 Batu Belah 5.00 rit 750,000.00 3,750,000.00

2 Cement (40 kg) 50.00 zak 50,000.00 2,500,000.00

3 Kris 1 - 2 1.00 rit 1,450,000.00 1,450,000.00

4 Pasir 2.00 rit 1,250,000.00 2,500,000.00







10,200,000.00
2 Pek. Slof, Kolom Balok, Lt






1 Pasir 2.00 rit 1,250,000.00 2,500,000.00

2 Kris 0.50 rit 1,450,000.00 725,000.00

3 Cement (40 kg) 75.00 zak 50,000.00 3,750,000.00

4 Papan 20 x 20 x 2 cm 200.00 lbr 7,000.00 1,400,000.00

5 Bambu Pancang Ø 10 - 13 cm 40.00 btg 35,000.00 1,400,000.00







9,775,000.00
3 Pek. Pasang Batu Bata + Plaster + Aci






1 Batu Bata 16,000.00 bh 500.00 8,000,000.00

2 Pasir 2.00 rit 1,250,000.00 2,500,000.00

3 Cement (40 kg) 100.00 zak 50,000.00 5,000,000.00







15,500,000.00
4 Pek. Kolong, Slop, Ring Balok, Kuda-kuda






1 Besi Ø 6 130.00 btg 22,000.00 2,860,000.00

2 Besi Ø 10 82.00 btg 86,000.00 7,052,000.00

3 Besi Ø 12 100.00 btg 107,000.00 10,700,000.00

4 Bendrat 1.00 rol 360,000.00 360,000.00







18,112,000.00
5 Pek. Kap Atap






1 Kayu 6 x 12 x 400 40.00 btg 220,000.00 8,800,000.00

2 Usuk 4 x 6 x 1,50 150.00 btg 8,500.00 1,275,000.00

3 Usuk 4 x 6 x 200 40.00 btg 20,000.00 800,000.00

4 Usuk 4 x 6 x 300 80.00 btg 32,000.00 2,560,000.00

5 Reng 2 x 3 x 400 10.00 pak 265,000.00 2,650,000.00







16,085,000.00
6 Pek. Kap






1 Genteng 6,000.00 buah 1,125.00 6,750,000.00

2 Kerpus 17.00 12,500.00 212,500.00







6,962,500.00
7 Pek. Plafond 100 m²



-

1 Kayu Glugu 4/6 x 4 m 80.00 btg 26,000.00 2,080,000.00

2 Eternit 100 x 100 170.00 15,250.00 2,592,500.00

3 Pek. Listplang Board 65.00 15,000.00 975,000.00







5,647,500.00
8 Pek. Lantai 1 RKB



-

1 Keramik 30 x 30 150.00 50,000.00 7,500,000.00

2 Pasir 1.00 rit 1,250,000.00 1,250,000.00

3 Cement (40 kg) 25.00 zak 50,000.00 1,250,000.00







10,000,000.00
9 Upah Tenaga 25% dari Jml Pekerjaan Seluruhnya
1.00 ls 23,070,500.00 23,070,500.00 23,070,500.00
10 Pek. Kusen Pintu dan Jendela
1.00 ls 12,500,000.00 12,500,000.00 12,500,000.00
11 Cakar Ayam 22 titik
22.00 titik 165,000.00 3,630,000.00 3,630,000.00
12 Pek. Urugan Padas
25.00 rit 575,000.00 14,375,000.00 14,375,000.00
13 Pek. Cat-catan Tembok dan Kayu
1.00 ls 6,500,000.00 6,500,000.00 6,500,000.00
14 Mebelair
1.00 RKB 8,500,000.00 8,500,000.00 8,500,000.00
15 Biaya administrasi + Laporan (DO) 5%
1.00 ls 4,614,100.00 4,614,100.00 4,614,100.00
Jumlah
165,471,600.00













Wedung, 11 Februari 2013











Ketua Pelaksana

Bendahara Pelaksana



























BUDIYONO, ST

MAHMUDI, S.Pd.I


Kata-kata yang terdapat di dalam file ini mungkin membantu anda melihat apakah file ini sesuai dengan yang dicari :

...Sheet rap rkb rencana anggaran pelaksanaan kegiatan pembangunan ruang kelas baru pekerjaan lokasi gedung sma islam sultan fatah wedung demak sumber dana apbn tahun no jenis volume harga satuan rp jumlah total pek slof kolom balok lt pasir rit kris cement kg zak papan x cm lbr bambu pancang oslash btg pasang batu bata plaster aci bh kolong slop ring kudakuda besi bendrat rol plat stegerperancah ls triplek genteng plafond m sup kayu glugu eternit listplang board catcatan lantai keramik upah tenaga dari jml seluruhnya kusen pintu dan jendela mebelair biaya administrasi laporan do februari ketua pelaksana bendahara budiyono st mahmudi spdi lab ipa pondasi belah kap atap usuk reng pak buah kerpus cakar ayam titik urugan padas tembok...