sheet 1 harsat daftar harga satuan bahan skpd dinas pertambangan dan energi provinsi ntt pekerjaan pembangunan rumah genset lokasi provinsi ntt tahun anggaran 2009 sumber dana apbd i no jenis ...

icon picture XLS Excel XLS | Diposting 06 Dec 2021 | 4 thn lalu
Berikut sebagian screen capture file ini. Geser ke kiri pada layar.
Sheet 1: HarSat
DAFTAR HARGA SATUAN BAHAN







SKPD
: DINAS PERTAMBANGAN DAN ENERGI PROVINSI NTT


PEKERJAAN
: PEMBANGUNAN RUMAH GENSET


LOKASI
: PROVINSI NTT


TAHUN ANGGARAN
: 2009


SUMBER DANA
: APBD I









No. JENIS BAHAN
SATUAN HARGA ONGKOS

QUARY ANGKUT HARGA SATUAN

(RP. ..,-) (RP. ..,-) (RP. ..,-)







1 BATU KALI/UTUH
M3 80,000 55,000 135,000
2 PASIR URUG/SIRTU
M3 70,000 25,000 95,000
3 PASIR PASANG/BETON
M3 140,000 35,000 175,000
4 BATU PECAH
M3 150,000 40,000 190,000
5 TANAH URUG
M3 60,000 20,000 80,000
6 PORTLAND CEMENT 50 KG
ZAK 45,000 2,500 47,500
7 BATU MERAH
Bh 500 25 525
8 BATU BATACO
Bh 2,100 100 2,200
9 PAKU BIASA
KG 17,500
17,500
10 PAKU SENG
KG 30,000
30,000
11 PAKU ANGKER
KG 20,000
20,000
12 BAUT DAN MUR PANJANG 20 CM
KG 17,500
17,500
13 BAJA STRIP U
KG 30,000
30,000
14 BESI BETON
KG 13,000 100 13,100
15 KAWAT BETON
KG 15,000 100 15,100
16 KAYU KOLOM KLAS II
M3 2,700,000 75,000 2,775,000
17 KAYU RANGKA KLAS II
M3 2,700,000 75,000 2,775,000
18 KAYU PAPAN KLAS II 3/25
M3 2,700,000 75,000 2,775,000
19 KAYU REGEL 5/7 KLAS II
M3 2,700,000 75,000 2,775,000
20 KAYU BEKISTING
M3 1,500,000 75,000 1,575,000
21 TRIPLEKS 2.8 MM
LEMBAR 80,000 1,000 81,000
22 BEBAK
LEMBAR 12,500 500 13,000
23 SENG GELOMBANG BJLS 0.20
LEMBAR 45,000 100 45,100
24 SENG PLAT BJLS 0.20
LEMBAR 45,000
45,000
25 KUNCI TANAM 2X PUTAR
BUAH 60,000
60,000
26 GRENDEL
BUAH 8,000
8,000
27 ENGSEL
BUAH 8,000
8,000
28 Oli Residu + Begesting
Liter 12,000
12,000
29 PENAMPUNG AIR
Zet 50,000
50,000
30 KLOSED JONGKOK
BUAH 125,000
125,000
31 ANGKER DOK
BUAH 17,500
17,500
32 LEM KAYU
LTR 10,000
10,000
33 PLAT STRIP
BUAH 3,500
3,500


















KUPANG, APRIL 2009




KEPALA DINAS PERTAMBANGAN DAN ENERGI




PROVINSI NUSA TENGGARA TIMUR
































DRS. BRIA YOHANES




Pembina Utama Muda





NIP. 620 018 831







DAFTAR HARGA SATUAN UPAH









SKPD : DINAS PERTAMBANGAN DAN ENERGI PROVINSI NTT



PEKERJAAN : PEMBANGUNAN RUMAH GENSET



LOKASI : PROVINSI NTT



TAHUN ANGGARAN : 2009



SUMBER DANA : APBD I









No. URAIAN
SATUAN



HARGA SATUAN


(RP. ..,-)








1 PEKERJA
ORANG/HARI 27,500

2 MANDOR
ORANG/HARI 50,000

3 TUKANG KAYU
ORANG/HARI 37,500

4 TUKANG BATU
ORANG/HARI 37,500

5 KEPALA TUKANG
ORANG/HARI 50,000



















KUPANG, APRIL 2009




KEPALA DINAS PERTAMBANGAN DAN ENERGI




PROVINSI NUSA TENGGARA TIMUR
































DRS. BRIA YOHANES




Pembina Utama Muda





NIP. 620 018 831

Sheet 2: ANALISA
DAFTAR ANALISA












SKPD : DINAS PERTAMBANGAN DAN ENERGI PROVINSI NTT






PEKERJAAN : PEMBANGUNAN RUMAH GENSET






LOKASI : PROVINSI NTT






THN. ANGGARAN : 2009






SUMBER DANA : APBD I














NO
JENIS PEKERJAAN VOL. SAT. PEKERJA HARGA JUMLAH TOTAL
kode ATAU SATUAN HARGA HARGA

MATERIAL (RP) (RP) (RP)
1
1 M3 Galian Tanah 0.625 Org pekerja 27,500.00 17,187.50 20,287.50



0.062 Org mandor 50,000.00 3,100.00











2
1 M3 Urug Tanah Kembali 0.192 Org Pekerja 27,500.00 5,280.00 6,230.00



0.019 Org Mandor 50,000.00 950.00





















3
1 M3 Urug Sirtu yang didatangkan 1.200 M3 Sirtu 95,000.00 114,000.00 122,125.00



0.250 Org pekerja 27,500.00 6,875.00




0.025 Org mandor 50,000.00 1,250.00











4
1 M3 Pasang Pondasi batu kosong 1.200 M3 batu kali/utuh 135,000.00 162,000.00 230,475.00



0.300 Org Pasir Urug/Sirtu 95,000.00 28,500.00




0.780 Org Pekerja 27,500.00 21,450.00




0.390 Org Tukang Batu 37,500.00 14,625.00




0.039 Org Kepala Tukang 50,000.00 1,950.00




0.039 Org Mandor 50,000.00 1,950.00











5
1 M3 Pasang Batu Kali (1 pc:4 psr) 1.100 M3 Batu 135,000.00 148,500.00 490,500.00



3.800 Zak Semen 47,500.00 180,500.00




0.520 M3 Pasir Pasang 175,000.00 91,000.00




0.600 Org Tukang 37,500.00 22,500.00




0.060 Org Kepala Tukang 50,000.00 3,000.00




1.500 Org Pekerja 27,500.00 41,250.00




0.075 Org Mandor 50,000.00 3,750.00





















6
1 M3 Pas Batu Merah 1 pc : 4 psr 70.0000 Bh Batu Merah 5 x 11x 22 525.00 36,750.00 71,731.25



0.2875 Zak Semen Portland 47,500.00 13,656.25




0.0430 M3 Pasir Pasang 175,000.00 7,525.00




0.0100 Org Kepala tukang 50,000.00 500.00




0.3200 Org Pekerja 27,500.00 8,800.00




0.1000 Org Tukang Batu 37,500.00 3,750.00




0.0150 Org Mandor 50,000.00 750.00











7 6.28.a 1 M3 Pasangan Konstruksi Kuda-kuda Kayu Klas 1.100 M3 Balok Klas II 2,775,000.00 3,052,500.00 3,749,000.00


II (tiang kayu + rangka atas) 0.800 Kg Paku biasa 17,500.00 14,000.00




15.000 Kg Besi Strip 3,500.00 52,500.00




0.200 Org Mandor 50,000.00 10,000.00




1.200 Org Kepala Tukang 50,000.00 60,000.00




12.000 Org Tukang kayu 37,500.00 450,000.00




4.000 Org Pekerja 27,500.00 110,000.00











8 6.31.a 1 M3 Pasang Gording Seng 5/7 Kayu Klas II 0.007 M3 Balok Kayu Klas II 2,775,000.00 19,425.00 28,425.00



0.100 Kg Paku Biasa 17,500.00 1,750.00




0.005 Org Mandor 50,000.00 250.00




0.010 Org Kepala Tukang 50,000.00 500.00




0.100 Org Tukang kayu 37,500.00 3,750.00




0.100 Org Pekerja 27,500.00 2,750.00





















9 6.54 1 M3 Pasang Rangka Dinding Kayu Kelas II 0.0195 M3 Balok Kayu Kals II 2,775,000.00 54,112.50 82,862.50



0.100 Kg Paku biasa 17,500.00 1,750.00




0.150 Org Pekerja 27,500.00 4,125.00




0.450 Org Tukang kayu 37,500.00 16,875.00




0.045 Org Kpl Tukang 50,000.00 2,250.00




0.075 Org Mandor 50,000.00 3,750.00











11
1 M3 Pekerjaan Kosen Pintu/Jendela 1.200 M3 BalokKayu Klas II 2,775,000.00 3,330,000.00 4,285,000.00


0.300 Org Mandor 50,000.00 15,000.00



2.000 Org Kpl Tukang 50,000.00 100,000.00



18.000 Org Tukang kayu 37,500.00 675,000.00




6.000 Org pekerja 27,500.00 165,000.00





















12
1 M2 Pasang Daun Pintu Rangkap 0.020 M3 Papan kls II 2,775,000.00 54,390.00 241,915.00


Trikpleks 2,8 mm 0.300 Ltr Lem Kayu 10,000.00 3,000.00




0.030 Kg Paku 17,500.00 525.00




1.000 Lbr Trikpleks 2.8 mm 81,000.00 81,000.00




0.600 Org Pekerja 27,500.00 16,500.00




2.000 Org Tukang kayu 37,500.00 75,000.00




0.200 Org Kpl Tukang 50,000.00 10,000.00




0.030 Org Mandor 50,000.00 1,500.00











13
1 M2 Pasang Daun Pintu seng Plat 0.017 M3 papan Klas II 2,775,000.00 47,175.00 131,052.50



0.083 Kg Paku biasa 17,500.00 1,452.50




0.720 lbr Seng Plat 0.20 45,000.00 32,400.00




0.250 Org Pekerja 27,500.00 6,875.00




1.000 Org Tukang Kayu 37,500.00 37,500.00




0.100 Org Kepala Tukang Kayu 50,000.00 5,000.00




0.013 Org Mandor 50,000.00 650.00











14 6 1 M2 Pas atap Seng Gel.BJLS 0.20 0.700 Lbr Seng Gel 45,100.00 31,570.00 38,320.00



0.020 Kg Paku seng 30,000.00 600.00




0.006 Org Mandor 50,000.00 300.00




0.006 Org Kpl Tukang 50,000.00 300.00




0.060 Org Tukang Kayu 37,500.00 2,250.00




0.120 Org Pekerja 27,500.00 3,300.00











15
1 M1 Pas .Seng Bubungan 0.20 0.278 Lbr Seng Plat 45,000.00 12,510.00 21,160.00



0.040 Kg paku seng 30,000.00 1,200.00




0.006 Org Mandor 50,000.00 300.00




0.008 Org Kpl.Tukang 50,000.00 400.00




0.070 Org Tukang kayu 37,500.00 2,625.00




0.150 Org Pekerja 27,500.00 4,125.00











16
1 M2 Pas Amping Seng 0.20 0.700 Lbr Seng Plat 45,000.00 31,500.00 43,575.00



0.030 Kg Paku seng 30,000.00 900.00




0.070 Org Mandor 50,000.00 3,500.00




0.009 Org Kpl.Tukang 50,000.00 450.00




0.090 Org Tukang kayu 37,500.00 3,375.00




0.140 Org Pekerja 27,500.00 3,850.00





















17
Pek. 1 Pasang Engsel 2.000 Buah Engsel 8,000.00 16,000.00 29,625.00



0.030 Org Pekerja 27,500.00 825.00




0.300 Org Tukang kayu 37,500.00 11,250.00




0.030 Org Kpl Tukang 50,000.00 1,500.00




0.001 Org Mandor 50,000.00 50.00











18
1 Bh Pasang Kunci Tanam 1.000 Buah Kunci Tanam 60,000.00 60,000.00 79,775.00



0.010 Org Pekerja 27,500.00 275.00




0.500 Org Tukang 37,500.00 18,750.00




0.010 Org Kepala Tukang 50,000.00 500.00




0.005 Org Mandor 50,000.00 250.00











19
1 Bh Pasang Grendel 1.000 Buah Grendel 8,000.00 8,000.00 14,837.50



0.015 Org Pekerja 27,500.00 412.50




0.150 Org Tukang 37,500.00 5,625.00




0.015 Org Kepala Tukang 50,000.00 750.00




0.001 Org Mandor 50,000.00 50.00











20
1 m3 Beton Bertulang 1 : 2 : 3


















Bahan 0.200 M3 Kayu/papan begesting 1,575,000.00 315,000.00 3,186,800.00



1.500 Kg Paku biasa 2 " - 5 " 17,500.00 26,250.00




0.400 Lt Minyak Begesting 12,000.00 4,800.00




150.000 Kg Besi Beton Polos 13,100.00 1,965,000.00




2.250 Kg Kawat Beton 15,100.00 33,975.00




8.070 Kg Semen Protland 47,500.00 383,325.00




0.520 M3 Pasir Beton 175,000.00 91,000.00




0.780 M3 Koral Beton 190,000.00 148,200.00













Upah 3.900 Org Pekerja 27,500.00 107,250.00




0.350 Org Tukang Batu 37,500.00 13,125.00




1.040 Org Tukang Kayu 37,500.00 39,000.00




1.050 Org Tukang Besi 37,500.00 39,375.00




0.245 Org Kepala Tukang 50,000.00 12,250.00




0.165 Org Mandor 50,000.00 8,250.00











21
1 m3 Beton Plat Septictank 1 : 2 : 3


















Bahan 0.334 M3 Kayu/papan begesting 1,575,000.00 526,050.00 2,727,097.50



1.500 Kg Baku biasa 2 " - 5 " 17,500.00 26,250.00




0.200 Lt Minyak Begesting 12,000.00 2,400.00




100.000 Kg Besi Beton Polos 13,100.00 1,310,000.00




1.350 Kg Kawat Beton 15,100.00 20,385.00




8.075 Kg Semen Protland 47,500.00 383,562.50




0.520 M3 Pasir Beton 175,000.00 91,000.00




0.780 M3 Koral Beton 190,000.00 148,200.00
1657946












Upah 3.900 Org Pekerja 27,500.00 107,250.00




0.350 Org Tukang Batu 37,500.00 13,125.00




1.040 Org Tukang Kayu 37,500.00 39,000.00




1.050 Org Tukang Besi 37,500.00 39,375.00




0.245 Org Kepala Tukang 50,000.00 12,250.00




0.165 Org Mandor 50,000.00 8,250.00











22
Memasang 1 bh Klosed Jongkok Monoblok 1.000 Buah Klosed Jongkok Porselin 125,000.00 125,000.00 300,625.00



0.150 Zak Semen Portland 47,500.00 7,125.00




0.010 M3 Pasir Pasang 175,000.00 1,750.00




1.000 Org Pekerja 27,500.00 27,500.00




1.500 Org Tukang 37,500.00 56,250.00




1.500 Org Kepala Tukang 50,000.00 75,000.00




0.160 Org Mandor 50,000.00 8,000.00











23
1 M1 Pengukuran dan Pemasangan 0.012 M3 Kayu 5/7 1,575,000.00 18,900.00 37,525.00


Bouwplank 0.020 Kg Paku Biasa > 5 cm 17,500.00 350.00




0.007 Org Kayu Papan 3/20 1,575,000.00 11,025.00




0.100 Org Pekerja 27,500.00 2,750.00




0.100 Org Tukang Kayu 37,500.00 3,750.00




0.010 Org Kepala Tukang 50,000.00 500.00




0.005 Org Mandor 50,000.00 250.00



























KUPANG, APRIL 2009








KEPALA DINAS PERTAMBANGAN








PROVINSI NUSA TENGGARA TIMUR
















































DRS. BRIA YOHANES








Pembina Utama Muda








NIP. 620 018 831



Sheet 3: RAB DAN REKAP 35 UNIT
RENCANA ANGGARAN BIAYA












SKPD : DINAS PERTAMBANGAN DAN ENERGI PROVINSI NTT






PEKERJAAN : PEMBANGUNAN RUMAH GENSET






LOKASI : PROVINSI NTT






TAHUN ANGGARAN : 2009






SUMBER DANA : APBD I















NO URAIAN KEGIATAN SAT. VOL. HARGA SAT. JUMLAH HARGA CATATAN(LORENS=RYAN): JIKA OE MAKA HARGA SATUAN UNTUK PENYEDIAAN AIR =34.600,00
(RP) (RP)





















I PEKERJAAN PERSIAPAN







1 Pembersihan lokasi

Ls 1.000 0.00 -

2 Pek. Pasang Bouwplank

M1 12.000 37,525.00 450,300.00 50,000.00
3 Penyediaan air kerja

Ls 1.000 50,000.00 50,000.00 60,000.00
4 Administrasi dan dokumentasi

Ls 1.000 20,000.00 20,000.00 34,000.00





JUMLAH I 520,300.00

II PEKERJAAN TANAH DAN URUGAN






1 Pek.Galian tanah pondasi

M3 1.200 20,287.50 24,345.00

2 Pek.Urugan tanah bekas galian

M3 0.300 6,230.00 1,869.00

3 Pek. Urugan sirtu peninggian lantai

M3 0.000 122,125.00 -







JUMLAH II 26,214.00
7500000
III PEKERJAAN PASANGAN, LANTAI , BETON DAN ACIAN






1 Pasangan Batu Kosong

M3 0.500 230,475.00 115,237.50

2 Pekerjaan Pasangan batu kali ( 1pc : 4ps )

M3 0.700 490,500.00 343,350.00

3 Pekerjaan Pasangan tembok batu merah ( 1pc : 4ps )

M3 1.500 71,731.25 107,596.88

4 Pekerjaan beton tumbuk (1:2:3) dudukan genset

M3 0.160 3,186,800.00 509,888.00

5 Pekerjaan lantai

M3 0.000 0.00 -







JUMLAH III 458,587.50

IV PEKERJAAN,KAYU,DINDING, KUSEN DAN ATAP







1 Pek. Rangka atap, Kayu Klas II

M3 0.880 28,425.00 25,014.00

2 Pek. Gording Seng Kayu Klas II

M2 0.000 0.00 -

3 Pekerjaan Rangka Dinding

M2 46.000 82,862.50 3,811,675.00

4 Pekerjaan kusen pintu dan jendela Jelusi

M3 0.120 4,285,000.00 514,200.00

5 Pek. Pemasangan jendela nako 7 Sisir

Unit 3.000 0.00 -

6 Pekerjaan daun pintu seng plat

M2 1.440 131,052.50 188,715.60

7 Pek. Pasang atap seng gelombang BJLS 0.20

M2 11.520 38,320.00 441,446.40

8 Pek. Pasang bubungan atap seng plat BJLS 0.20

M' 0.000 0.00 -

9 Pek. Pasang Amping seng gelombang BJLS 0.20

M2 0.000 0.00 -
13,000,000






JUMLAH IV 4,981,051.00
6,110,390
V PEKERJAAN PENGGANTUNG DAN PENGUNCI





611,039
1 Pek. Pemasangan Engsel

Psg 1.000 29,625.00 29,625.00
6,721,429
2 Pek. Pemasangan Kunci Tanam

Psg 1.000 79,775.00 79,775.00

3 Pek. Pemasangan Grendel

Buah 1.000 14,837.50 14,837.50







JUMLAH V 124,237.50
(6,278,571)






TOTAL 1 - V 6,110,390


























KUPANG, APRIL 2009








KEPALA DINAS PERTAMBANGAN








PROVINSI NUSA TENGGARA TIMUR
















































DRS. BRIA YOHANES







Pembina Utama Muda









NIP. 110037178































































REKAPITULASI












SKPD
: DINAS PERTAMBANGAN DAN ENERGI PROVINSI NTT





PEKERJAAN
: PEMBANGUNAN RUMAH GENSET


404

LOKASI
: PROVINSI NTT





TAHUN ANGGARAN
: 2009





SUMBER DANA
: APBD I















NO JENIS PEKERJAAN HARGA (Rp)
















A PEKERJAAN RUMAH GENSET



Rp6,110,390.00
611,039








6,721,429




















B PPN 10%



Rp611,039.00












C JUMLAH TOTAL



Rp6,721,429.00












D DIBULATKAN



Rp6,721,000.00






















TERBILANG : ENAM JUTA TUJUH RATUS DUA PULUH SATU RIBU RUPIAH







(7,779,000)













































KUPANG, APRIL 2009








KEPALA DINAS PERTAMBANGAN








PROVINSI NUSA TENGGARA TIMUR















































DRS. BRIA YOHANES








Pembina Utama Muda









NIP. 620 018 831



Kata-kata yang terdapat di dalam file ini mungkin membantu anda melihat apakah file ini sesuai dengan yang dicari :

...Sheet harsat daftar harga satuan bahan skpd dinas pertambangan dan energi provinsi ntt pekerjaan pembangunan rumah genset lokasi tahun anggaran sumber dana apbd i no jenis ongkos quary angkut rp batu kaliutuh m pasir urugsirtu pasangbeton pecah tanah urug portland cement kg zak merah bh bataco paku biasa seng angker baut mur panjang cm baja strip u besi beton kawat kayu kolom klas ii rangka papan regel bekisting tripleks mm lembar bebak gelombang bjls plat kunci tanam x putar buah grendel engsel oli residu begesting liter penampung air zet klosed jongkok dok lem ltr kupang april kepala nusa tenggara timur drs bria yohanes pembina utama muda nip upah uraian pekerja oranghari mandor tukang analisa thn vol sat jumlah total kode atau material galian org kembali sirtu yang didatangkan pasang pondasi kosong kali pc psr semen pas a pasangan konstruksi kudakuda balok tiang atas gording...

no reviews yet
Please Login to review.