PERUSAHAAN DAERAH AIR MINUM | ||||||||||
KOTA MALANG | -109 | |||||||||
69 | ||||||||||
REKAPITULASI RENCANA ANGGARAN BIAYA | ||||||||||
PEKERJAAN | : | Pembuatan Tabung Pompa Water Tank Buring Tengah | ||||||||
L O K A S I | : | Tandon Air Buring Tengah | ||||||||
Kota Malang | ||||||||||
No. | URAIAN PEKERJAAN | J U M L A H | ||||||||
1 | 2 | 3 | ||||||||
I. | PEKERJAAN PERSIAPAN : | Rp. | 100,000.00 | |||||||
II. | PEKERJAAN TANAH : | Rp. | 3,185,180.32 | |||||||
III. | PEKERJAAN BETON : | Rp. | 1,529,245.60 | |||||||
VI | PEKERJAAN BESI DAN PIPA : | |||||||||
1 | Bahan | |||||||||
a. | GI | Rp. | PDAM | |||||||
b. | PE PN 12.5 | Rp. | PDAM | |||||||
c. | Accesories | Rp. | PDAM | |||||||
2 | Upah | |||||||||
a. | Pemasangan Pipa GI | Rp. | 7,372,453.60 | |||||||
b. | Pemasangan PE 12,5 | Rp. | 463,388.63 | |||||||
c. | Pengeboran | Rp. | 5,166,187.50 | |||||||
d. | Biaya Tapping ( Penyambungan ) | Rp. | 3,207,127.70 | |||||||
V | PEKERJAAN PENGECATAN : | Rp. | 58,866.04 | |||||||
VI | PEKERJAAN PENYELESAIAN : | Rp. | 100,000.00 | |||||||
J u m l a h | Rp. | 21,182,449.38 | ||||||||
Jumlah Total | Rp. | 21,182,449.38 | ||||||||
Dibulatkan | Rp. | 21,182,000.00 | ||||||||
Terbilang : ( Dua puluh satu juta seratus delapan puluh dua ribu ) | ||||||||||
Keterangan : | ||||||||||
- | Analisa berdasarkan satuan SNI | Dua puluh satu juta seratus delapan puluh dua ribu | ||||||||
- | Harga belum termasuk PPN 10% | |||||||||
Malang, ...................................... | ||||||||||
Dibuat oleh, | ||||||||||
Manajer Perencanaan Teknik | ||||||||||
ISWAGIANTONO, ST | ||||||||||
NPP. 03920283 | ||||||||||
Mengetahui, | Mengetahui, | |||||||||
Direktur Adm. & Keuangan | Direktur Teknik | |||||||||
ANITA SARI, SH, MH | Ir. H. TEGUH CAHYONO. MAB. | |||||||||
Disetujui, | ||||||||||
Untuk Dilaksanakan | ||||||||||
Direktur Utama | ||||||||||
H. M JEMIANTO. | ||||||||||
Malang, ........................................... | ||||||||||
Diperiksa, | Dibuat oleh, | |||||||||
Direktur Teknik | Manajer Perencanaan Teknik | |||||||||
Ir. H. BAMBANG PURJITO, MM. | KUSBIANTO, ST. | |||||||||
NPP. 08830083 | NPP. 01840096 | |||||||||
Disetujui, | ||||||||||
Untuk Dilaksanakan | ||||||||||
Direktur Utama | ||||||||||
Drs. H. HERYADI SANTOSO, MSi. | ||||||||||
NPP. 01810027 | ||||||||||
Rp. | 21,182,449.38 | |||||||||
BIAYA SURVEY & DESIGN 2 % | Rp. | 423,648.99 | ||||||||
BIAYA UMUM 2 % | Rp. | 423,648.99 |
PERUSAHAAN DAERAH AIR MINUM | |||||||||||
KOTA MALANG | |||||||||||
RENCANA ANGGARAN BIAYA | |||||||||||
PEKERJAAN | : | Pembuatan Tabung Pompa Water Tank Buring Tengah | |||||||||
L O K A S I | : | Tandon Air Buring Tengah | |||||||||
Kota Malang | |||||||||||
HARGA ( Rp. ) | |||||||||||
No. | URAIAN PEKERJAAN | SATUAN | VOLUME | ANALISA | SATUAN | JML. HARGA | JML. HARGA | ||||
SATUAN | SELURUH | ||||||||||
1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | ||||
I. | PEKERJAAN PERSIAPAN : | ||||||||||
Pengukuran / Uit Set | - | - | pas | 100,000.00 | 100,000.00 | ||||||
100,000.00 | |||||||||||
II. | PEKERJAAN TANAH : | ||||||||||
Galian tanah biasa h=1m | m3 | 6.25 | : B.01 | 66,137.50 | 413,359.38 | ||||||
Galian Pipa Ø200mm panjang 21m | m3 | 6.62 | : B.01 | 66,137.50 | 437,499.56 | ||||||
Pek. Urugan Tanah | m3 | 13.97 | : B.12 | 167,120.60 | 2,334,321.38 | ||||||
3,185,180.32 | |||||||||||
III. | PEKERJAAN BETON : | ||||||||||
Pembuatan Thrust Block | m3 | 0.14 | : G.32 | 10,619,761.10 | 1,529,245.60 | ||||||
1,529,245.60 | |||||||||||
IV. | PEKERJAAN BESI DAN PIPA : | ||||||||||
1. | Bahan | ||||||||||
a | GI | ||||||||||
Chasing Pipa GI Ø12'' | m' | 6.00 | pas | PDAM | PDAM | ||||||
PIPA GI Ø4'' | m' | 7.30 | pas | PDAM | PDAM | ||||||
PDAM | |||||||||||
b | PE PN 12.5 | ||||||||||
Pipa PE PN 12.5 Ø 200 | m' | 21.00 | pas | PDAM | PDAM | ||||||
PDAM | |||||||||||
c | Accesories | ||||||||||
Anker baut | Kg | 2.86 | pas | PDAM | PDAM | ||||||
Blind flange Ø12'' | bh | 1.00 | pas | PDAM | PDAM | ||||||
Plat untuk Blind Flange Ø12'' tbl 2cm | bh | 1.00 | pas | PDAM | PDAM | ||||||
Flange Ø 4" | bh | 4.00 | pas | PDAM | PDAM | ||||||
Flange Ø 12" | bh | 2.00 | pas | PDAM | PDAM | ||||||
Pak Karet Ø12'' | bh | 3.00 | pas | PDAM | PDAM | ||||||
Pak Karet Ø4'' | bh | 9.00 | pas | PDAM | PDAM | ||||||
Pak Karet Ø8'' | bh | 2.00 | bh | PDAM | PDAM | ||||||
Mur baut dan ring Flange Ø12'' | bh | 36.00 | pas | PDAM | PDAM | ||||||
Mur baut dan ring Flange Ø4'' | bh | 32.00 | pas | PDAM | PDAM | ||||||
All Flange Bend Ø 4" 90◦ | bh | 1.00 | pas | PDAM | PDAM | ||||||
All Flange Bend Ø 4" 45◦ | bh | 2.00 | pas | PDAM | PDAM | ||||||
All Flange Bend Ø 8'' 45° | bh | 1.00 | pas | PDAM | PDAM | ||||||
Valve Ø 4" | bh | 1.00 | pas | PDAM | PDAM | ||||||
Flange Reducer Ø 4" x Ø8" | bh | 1.00 | pas | PDAM | PDAM | ||||||
Flange Adaptor Universal Ø8" | bh | 4.00 | pas | PDAM | PDAM | ||||||
Flange Adaptor Universal Ø4" | bh | 2.00 | pas | PDAM | PDAM | ||||||
Air Release Ø1'' | bh | 1.00 | pas | PDAM | PDAM | ||||||
All Flange Tee Ø 12 x Ø 8 | bh | 1.00 | pas | PDAM | PDAM | ||||||
Manometer Ø1/2" | bh | 1.00 | pas | PDAM | PDAM | ||||||
Double Nepel Ø1/2" | bh | 1.00 | pas | PDAM | PDAM | ||||||
Shock drat dalam dilas ke pipa | bh | 1.00 | pas | PDAM | PDAM | ||||||
Stop Kran Ø1/2" | bh | 1.00 | pas | PDAM | PDAM | ||||||
Tapping Saddle Ø500x200 mm | bh | 1.00 | pas | PDAM | PDAM | ||||||
PDAM | |||||||||||
2. | Upah | ||||||||||
a. | Pemasangan Pipa GI | ||||||||||
Pasang Chasing Ø12'' h=6 m | m' | 6.00 | : R.39 | 124,090.73 | 744,544.41 | ||||||
Pasang pipa Ø4'' h=7,3 m | m' | 7.30 | : R.35 | 24,511.75 | 178,935.78 | ||||||
Pengelasan pipa chasing Ø12'' | cm' | 753.60 | : K.07 | 4,932.45 | 3,717,096.69 | ||||||
Pengelasan pipa Ø4'' | cm' | 251.20 | : K.07 | 4,932.45 | 1,239,032.23 | ||||||
Pengelasan anker baut | cm | 175.34 | : K.08 | 4,932.45 | 864,844.50 | ||||||
Potong pipa Ø12'' | cm | 94.20 | pas | 4,000.00 | 376,800.00 | ||||||
Potong pipa Ø4'' | cm | 62.80 | pas | 4,000.00 | 251,200.00 | ||||||
7,372,453.60 | |||||||||||
b. | Pemasangan PE 12,5 | ||||||||||
Pasang Pipa PE PN 12.5 Ø 200 | m' | 21.00 | : R.117 | 22,066.13 | 463,388.63 | ||||||
463,388.63 | |||||||||||
c. | Pengeboran | ||||||||||
Bor Ø 60cm h= 5,2 m | m' | 5.20 | : B.24 | 656,718.75 | 3,414,937.50 | ||||||
Bor crossing pipa Ø200mm h=4 m | m' | 4.00 | : B.22 | 437,812.50 | 1,751,250.00 | ||||||
5,166,187.50 | |||||||||||
d | Biaya Tapping ( Penyambungan ) | ||||||||||
Pipa PE PN 12.5 Ø 500x200 | Titik | 1.00 | : R.164d | 3,207,127.70 | 3,207,127.70 | ||||||
3,207,127.70 | |||||||||||
V. | PEKERJAAN PENGECATAN : | ||||||||||
Cat besi (epoxy zincromit) | m² | 0.50 | : N.25 | 117,235.00 | 58,866.04 | ||||||
58,866.04 | |||||||||||
VI. | PEKERJAAN PENYELESAIAN : | ||||||||||
Pembersihan lokasi | - | - | ls | 100,000.00 | 100,000.00 | ||||||
100,000.00 | |||||||||||
Urug Pasir | m3 | #NAME? | Err:509 | Err:509 | Err:509 | ||||||
Pas. Batu Kali | m3 | #NAME? | Err:509 | Err:509 | Err:509 | ||||||
Kawat Tali Galvanis 3mm | Kg | 19.00 | Err:509 | Err:509 | Err:509 | ||||||
Moor baut ф 16 mm | bh | 19.00 | Err:509 | Err:509 | Err:509 | ||||||
Ring ф 16 mm | bh | 76.00 | Err:509 | Err:509 | Err:509 | ||||||
Kawat duri | m1 | 114.00 | Err:509 | Err:509 | Err:509 | ||||||
II. | PEKERJAAN TANAH : | ||||||||||
Galian Tanah | m3 | 0.57 | Err:509 | Err:509 | Err:509 | ||||||
Err:509 | |||||||||||
III. | PEKERJAAN PASANGAN : | ||||||||||
Plesteran | m2 | #REF! | : E.06 | 23,740.28 | #REF! | ||||||
#REF! |
PERUSAHAAN DAERAH AIR MINUM | ||||||||||
KOTA MALANG | -109 | |||||||||
69 | ||||||||||
REKAPITULASI RENCANA ANGGARAN BIAYA | ||||||||||
PEKERJAAN | : | Pembuatan Tabung Pompa Water Tank Buring Tengah | ||||||||
L O K A S I | : | Tandon Air Buring Tengah | ||||||||
Kota Malang | ||||||||||
No. | URAIAN PEKERJAAN | J U M L A H | ||||||||
1 | 2 | 3 | ||||||||
I. | PEKERJAAN PERSIAPAN : | Rp. | 100,000.00 | |||||||
II. | PEKERJAAN TANAH : | Rp. | 3,185,180.32 | |||||||
III. | PEKERJAAN BETON : | Rp. | 1,529,245.60 | |||||||
VI | PEKERJAAN BESI DAN PIPA : | |||||||||
1 | Bahan | |||||||||
a. | GI | Rp. | 14,459,717.80 | |||||||
b. | PE PN 12.5 | Rp. | 9,712,500.00 | |||||||
c. | Accesories | Rp. | 133,243,033.57 | |||||||
2 | Upah | |||||||||
a. | Pemasangan Pipa GI | Rp. | 7,372,453.60 | |||||||
b. | Pemasangan PE 12,5 | Rp. | 463,388.63 | |||||||
c. | Pengeboran | Rp. | 5,166,187.50 | |||||||
d. | Biaya Tapping ( Penyambungan ) | Rp. | 3,207,127.70 | |||||||
V | PEKERJAAN PENGECATAN : | Rp. | 58,866.04 | |||||||
VI | PEKERJAAN PENYELESAIAN : | Rp. | 100,000.00 | |||||||
J u m l a h | Rp. | 178,597,700.75 | ||||||||
PPN 10% | Rp. | 17,859,770.08 | ||||||||
Jumlah Total | Rp. | 196,457,470.83 | ||||||||
Dibulatkan | Rp. | 196,457,000.00 | ||||||||
Terbilang : ( Seratus sembilan puluh enam juta empat ratus lima puluh tujuh ribu ) | (160,737,930.68) | |||||||||
Keterangan : | ||||||||||
- | Analisa berdasarkan satuan SNI | Seratus sembilan puluh enam juta empat ratus lima puluh tujuh ribu | ||||||||
- | Harga sudah termasuk PPN 10% | |||||||||
Malang, ...................................... | ||||||||||
Dibuat oleh, | ||||||||||
Manajer Perencanaan Teknik | ||||||||||
ISWAGIANTONO, ST | ||||||||||
NPP. 03920283 | ||||||||||
Mengetahui, | Mengetahui, | |||||||||
Direktur Adm. & Keuangan | Direktur Teknik | |||||||||
ANITA SARI, SH, MH | Ir. H. TEGUH CAHYONO. MAB. | |||||||||
Disetujui, | ||||||||||
Untuk Dilaksanakan | ||||||||||
Direktur Utama | ||||||||||
H. M JEMIANTO. | ||||||||||
Malang, ........................................... | ||||||||||
Diperiksa, | Dibuat oleh, | |||||||||
Direktur Teknik | Manajer Perencanaan Teknik | |||||||||
Ir. H. BAMBANG PURJITO, MM. | KUSBIANTO, ST. | |||||||||
NPP. 08830083 | NPP. 01840096 | |||||||||
Disetujui, | ||||||||||
Untuk Dilaksanakan | ||||||||||
Direktur Utama | ||||||||||
Drs. H. HERYADI SANTOSO, MSi. | ||||||||||
NPP. 01810027 | ||||||||||
Rp. | 178,597,700.75 | |||||||||
BIAYA SURVEY & DESIGN 2 % | Rp. | 3,571,954.02 | ||||||||
BIAYA UMUM 2 % | Rp. | 3,571,954.02 |