193x Filetype PDF File size 0.31 MB Source: www.pjm.com
PJM Generator Interconnection Request System Impact Study Report Queue Position #Q72 Mansfield - S. Troy 115 KV 60 MW (12 MW Capacity) November 2009 (REVISED) © PJM Interconnection 2009. All rights reserved. 1 PJMDOCS-#550624-v2-Q72_SIS_Report.DOC Preface The intent of this System Impact Study is to determine a plan, with cost and construction time estimates, to connect the subject generation to the PJM network at a location specified by the Interconnection Customer. The Interconnection Customer may request the interconnection of generation as a capacity resource or as an energy-only resource. As a requirement for interconnection, the Interconnection Customer may be responsible for the cost of constructing: (1) Direct Connections, which are new facilities and/or facilities upgrades needed to connect the generator to the PJM network, and (2) Network Upgrades, which are facility additions, or upgrades to existing facilities, that are needed to maintain the reliability of the PJM system. In some instances a generator interconnection may not be responsible for 100% of the identified network upgrade cost because other transmission network uses, e.g. another generation interconnection, may also contribute to the need for the same network reinforcement. The possibility of sharing the reinforcement costs with other projects may be identified in the feasibility study, but the actual allocation will be deferred until the impact study is performed. The System Impact Study estimates do not include the feasibility, cost, or time required to obtain property rights and permits for construction of the required facilities. The Interconnection Customer is responsible for the right of way, real estate, and construction permit issues. For properties currently owned by Transmission Owners, the costs may be included in the study. © PJM Interconnection 2009. All rights reserved. 2 PJMDOCS-#550624-v2-Q72_SIS_Report.DOC Queue Position #Q72 kV System Impact Study Report GENERAL The Queue Position #Q72 project was studied as a 110MW (22MW Capacity Resource) injection on Mansfield - S. Troy 115kV line in the Penelec area. Queue position #Q72 was evaluated for compliance with reliability criteria for summer peak conditions in 2011. The load flow portion of this study assumes the wind farm has the capability to maintain unity power factor at the collector bus of the wind farm. To solve the voltage collapse on the Farmers Valley to E Towanda 115kV line with Q72 at full output (110 MW) and the S Troy – P47 contingency, the following system reinforcement is required. Construction of 30 miles of new 230 kV line from Mansfield to Grover using 1033 ACSR conductor, installation of a four breaker 230kV ring bus at Grover, installation of a 230kV and 115kV breaker and a 230/115 kV transformer at Mansfield and reconfiguration of Mansfield into a 115kV ring substation - estimated to cost $60,998,100 (figure 2). The following analysis assumes this Network Upgrade is in place. DIRECT CONNECTION FACILITIES It is estimated the construction of the switching-station will take approximately 24 months following the execution of an Interconnection Construction Service Agreement (CSA). This does not meet the Interconnection Customer’s requested in-service date. The Interconnection Customer, FirstEnergy, and PJM should meet to discuss how to proceed. Specific timing and milestones for completion of construction activities will be specified in the Interconnection Service Agreement and Construction Service Agreement The proposed Interconnection Facilities must be designed in accordance with the FirstEnergy Applicable Standards posted on the PJM Website titled “Requirements for Transmission Connected Facilities” document. http://www.pjm.com/planning/design-engineering/to-tech-standards.aspx It will be the Interconnection Customer’s responsibility to obtain any needed right-of-way between the plant site and FirstEnergy’s facilities. Below are estimates for the engineering/construction associated with Direct Connection requirements based upon similar projects that have been designed and/or constructed. Item Description PJM Network Conceptual Cost Upgrade # Estimate 1 New 115 kV 3-breaker ring bus termination n1509 $3,220,500 point at a new interconnection substation approximately 10.6 miles east of Mansfield 115 kV Substation. 2 Engineering and Oversight of the Customer n1510 $63,500 Facility substation include relaying © PJM Interconnection 2009. All rights reserved. 3 PJMDOCS-#550624-v2-Q72_SIS_Report.DOC Item Description PJM Network Conceptual Cost Upgrade # Estimate 3 New 115 kV tap structure extending from n1511 $79,700 the Mansfield-South Troy 115 kV line to interconnection substation. 4 115 kV transmission line extending from N/A N/A the new tap structure in the Mansfield-South Developer cost. Line Troy 115 kV line to the generation plant built, owned and interconnection substation. maintained by the developer. 5 Fiber optic cable from Mansfield to P47 n1512 $1,327,700 (Everts Drive Sub) approximately 15.5 miles. 6 Relay and control work at Mansfield 115 n1513 $226,700 kV Substation. 7 Relay and control work at P47 115 kV n1514 $226,700 Substation. Conceptual Estimate: $5,371,500 Estimated Lead Time: 2.0 years from signed CSA Notes: Detailed Engineering & Construction Estimates TBD during Facilities Study The above estimates do not include 1) tax gross-up, if required, 2) property costs and site development up to rough grade which is to be provided by the Interconnection Customer, 3) interconnection metering and generation SCADA to be provided by the Interconnection Customer, 4) engineering and field activities for design review and commissioning of the Interconnection Customer’s facilities, and 5) Real estate costs that may be required for right-of- way easements to extend the 115 kV line. The Interconnection Customer is required to meet the metering requirements of Attachment 1. © PJM Interconnection 2009. All rights reserved. 4 PJMDOCS-#550624-v2-Q72_SIS_Report.DOC
no reviews yet
Please Login to review.