342x Filetype PDF File size 0.31 MB Source: www.pjm.com
PJM Generator Interconnection Request
System Impact Study Report
Queue Position #Q72
Mansfield - S. Troy 115 KV
60 MW
(12 MW Capacity)
November 2009
(REVISED)
© PJM Interconnection 2009. All rights reserved.
1
PJMDOCS-#550624-v2-Q72_SIS_Report.DOC
Preface
The intent of this System Impact Study is to determine a plan, with cost and construction time
estimates, to connect the subject generation to the PJM network at a location specified by the
Interconnection Customer. The Interconnection Customer may request the interconnection of
generation as a capacity resource or as an energy-only resource. As a requirement for
interconnection, the Interconnection Customer may be responsible for the cost of constructing:
(1) Direct Connections, which are new facilities and/or facilities upgrades needed to connect the
generator to the PJM network, and (2) Network Upgrades, which are facility additions, or
upgrades to existing facilities, that are needed to maintain the reliability of the PJM system.
In some instances a generator interconnection may not be responsible for 100% of the identified
network upgrade cost because other transmission network uses, e.g. another generation
interconnection, may also contribute to the need for the same network reinforcement. The
possibility of sharing the reinforcement costs with other projects may be identified in the
feasibility study, but the actual allocation will be deferred until the impact study is performed.
The System Impact Study estimates do not include the feasibility, cost, or time required to obtain
property rights and permits for construction of the required facilities. The Interconnection
Customer is responsible for the right of way, real estate, and construction permit issues. For
properties currently owned by Transmission Owners, the costs may be included in the study.
© PJM Interconnection 2009. All rights reserved.
2
PJMDOCS-#550624-v2-Q72_SIS_Report.DOC
Queue Position #Q72 kV System Impact Study Report
GENERAL
The Queue Position #Q72 project was studied as a 110MW (22MW Capacity Resource)
injection on Mansfield - S. Troy 115kV line in the Penelec area. Queue position #Q72 was
evaluated for compliance with reliability criteria for summer peak conditions in 2011. The load
flow portion of this study assumes the wind farm has the capability to maintain unity power
factor at the collector bus of the wind farm.
To solve the voltage collapse on the Farmers Valley to E Towanda 115kV line with Q72 at full
output (110 MW) and the S Troy – P47 contingency, the following system reinforcement is
required. Construction of 30 miles of new 230 kV line from Mansfield to Grover using 1033
ACSR conductor, installation of a four breaker 230kV ring bus at Grover, installation of a 230kV
and 115kV breaker and a 230/115 kV transformer at Mansfield and reconfiguration of Mansfield
into a 115kV ring substation - estimated to cost $60,998,100 (figure 2). The following analysis
assumes this Network Upgrade is in place.
DIRECT CONNECTION FACILITIES
It is estimated the construction of the switching-station will take approximately 24 months
following the execution of an Interconnection Construction Service Agreement (CSA). This
does not meet the Interconnection Customer’s requested in-service date. The Interconnection
Customer, FirstEnergy, and PJM should meet to discuss how to proceed. Specific timing and
milestones for completion of construction activities will be specified in the Interconnection
Service Agreement and Construction Service Agreement
The proposed Interconnection Facilities must be designed in accordance with the FirstEnergy
Applicable Standards posted on the PJM Website titled “Requirements for Transmission
Connected Facilities” document.
http://www.pjm.com/planning/design-engineering/to-tech-standards.aspx
It will be the Interconnection Customer’s responsibility to obtain any needed right-of-way
between the plant site and FirstEnergy’s facilities.
Below are estimates for the engineering/construction associated with Direct Connection
requirements based upon similar projects that have been designed and/or constructed.
Item Description PJM Network Conceptual Cost
Upgrade # Estimate
1 New 115 kV 3-breaker ring bus termination n1509 $3,220,500
point at a new interconnection substation
approximately 10.6 miles east of Mansfield
115 kV Substation.
2 Engineering and Oversight of the Customer n1510 $63,500
Facility substation include relaying
© PJM Interconnection 2009. All rights reserved.
3
PJMDOCS-#550624-v2-Q72_SIS_Report.DOC
Item Description PJM Network Conceptual Cost
Upgrade # Estimate
3 New 115 kV tap structure extending from n1511 $79,700
the Mansfield-South Troy 115 kV line to
interconnection substation.
4 115 kV transmission line extending from N/A N/A
the new tap structure in the Mansfield-South Developer cost. Line
Troy 115 kV line to the generation plant built, owned and
interconnection substation. maintained by the
developer.
5 Fiber optic cable from Mansfield to P47 n1512 $1,327,700
(Everts Drive Sub) approximately 15.5
miles.
6 Relay and control work at Mansfield 115 n1513 $226,700
kV Substation.
7 Relay and control work at P47 115 kV n1514 $226,700
Substation.
Conceptual Estimate: $5,371,500
Estimated Lead Time: 2.0 years from signed CSA
Notes:
Detailed Engineering & Construction Estimates TBD during Facilities Study
The above estimates do not include 1) tax gross-up, if required, 2) property costs and site
development up to rough grade which is to be provided by the Interconnection Customer, 3)
interconnection metering and generation SCADA to be provided by the Interconnection
Customer, 4) engineering and field activities for design review and commissioning of the
Interconnection Customer’s facilities, and 5) Real estate costs that may be required for right-of-
way easements to extend the 115 kV line.
The Interconnection Customer is required to meet the metering requirements of Attachment 1.
© PJM Interconnection 2009. All rights reserved.
4
PJMDOCS-#550624-v2-Q72_SIS_Report.DOC
no reviews yet
Please Login to review.