jagomart
digital resources
picture1_Report Pdf 94746 | Q55 Imp


 158x       Filetype PDF       File size 0.54 MB       Source: www.pjm.com


File: Report Pdf 94746 | Q55 Imp
generation interconnection pjm impact study report revised for pjm generation interconnection request queue position q55 snowy creek 138kv project march 2012 pjm interconnection 2012 all rights reserved 1 pjmdocs 691313v1 ...

icon picture PDF Filetype PDF | Posted on 17 Sep 2022 | 3 years ago
Partial capture of text on file.
                   
                                                                                                                                                                              
                                                                             
                                                                             
                                          Generation Interconnection  
                                            PJM Impact Study Report 
                                                                   Revised 
                                                                             
                                                                         For 
                                                                             
                         PJM Generation Interconnection Request 
                                                   Queue Position Q55 
                                                                             
                                          Snowy Creek 138kV Project 
                                                                             
                                                                             
                                                                             
                                                                             
                                                                             
                                                                                                                                       
                                                                                                                                       
                                                                                                                                       
                                                                                                                                       
                                                                                                                                       
                                                                                                                                       
                                                                                                                                       
                                                                                                                                       
                                                                                                                                       
                                                                                                                                       
                                                                                                                                       
                                                                                                                                       
                                                                                                                    March, 2012 
                  © PJM Interconnection 2012.  All rights reserved.    1                             PJMDOCS-# 691313v1 
                                                                                            Q55 System Impact Study Report 
                   
                          
                                                                                                                                                                                     
                                                                                   System Impact Study 
                                                                                                        
                                                                  Snowy Creek 138kV Generation Project 
                                                                                                        
                          
                          
                         Introduction 
                          
                         This System Impact Study report provides the documentation of an assessment that has been 
                         performed by PJM Interconnection, L.L.C. and  FirstEnergy (FE) in response to a request made 
                         by AES Wind, LLC for the connection of a 62.5 MW (12.5 MW Capacity) Snowy Creek 138kV  
                         Wind Farm Generation Project to the MonPower Transmission System. AES Wind, LLC has a 
                         proposed commercial operation date of June 2013 for the proposed Snowy Creek 138kV facility. 
                         As per the PJM study process, the Snowy Creek 138kV  Project assessment was accomplished 
                         by:  1.  Evaluating  the  reliability  impact  of  the  proposed  facilities  and  connection  on  the 
                         interconnected  transmission  system  by  the  performance  of  a  power  flow  study;  2.  Ensuring 
                         compliance with the NERC, ReliabilityFirst, PJM and FE Reliability Standards by identifying 
                         the system reinforcements that will need to be installed for an interconnection of the proposed 
                         project;  3.  Coordinating  and  cooperating  with  the  PJM  staff  and  AES  Wind,  LLC  by 
                         participating in project meetings and issuing this report as a part of the PJM study process; 4. 
                         Performing a Steady State, Short-Circuit and Dynamics Study as necessary; 5. Conducting all 
                         studies in accordance with the PJM Manuals, the "FE Requirements for Transmission Connected 
                         Facilities", and the "FE Study Guide". 
                          
                         Connection Facilities 
                          
                         In compliance with the PJM planning protocol, AES Wind, LLC has submitted a "System Impact 
                         Study Agreement" to PJM and a proposed single line diagram that identifies its plan to construct 
                         a  Wind Turbine Generation Project on a property in Preston County, West Virginia, that is 
                         approximately 3 miles from Snowy Creek substation. AES Wind, LLC reduced the size of the 
                         project to a total capability of 62.5 MW (12.5 MW Capacity) on 3/1/2010. For purposes of this 
                         report,  it  has  therefore  been  designated  as  the  Snowy  Creek  138kV  Project  to  reflect  its 
                         interconnection voltage and its proximity to Snowy Creek substation. 
                          
                         The interconnection of this project will be accomplished by expanding Snowy Creek substation 
                         and installing 3-138kV breakers and associated facilities. A summary of the Snowy Creek 138kV 
                         Project  direct  connection  facilities  is  shown  on  Attachment  3.  The  one-line  is  shown  in 
                         Attachment 2. 
                         © PJM Interconnection 2012.  All rights reserved.                      2                                        PJMDOCS-# 691313v1 
                                                                                                                            Q55 System Impact Study Report 
                          
                   
                                                                                                                                                                              
                  PJM Analysis Summary 
                   
                  This  portion  of  this  report  was  prepared  by  the  PJM  Interconnection  Engineering  staff.    It 
                  identifies the overloads and violations found on the Transmission system.  These overloads are 
                  addressed as required, later in this report with associated reinforcements and upgrades. 
                   
                  Network Impacts 
                   
                  The Queue Project #Q55 was studied as a 62.5 MW(Capacity: 12.5 MW) injection at Snowy 
                  Creek substation in the FE  area. Project #Q55 was evaluated for compliance with reliability 
                  criteria for summer peak conditions in 2011. The load flow portion of this study assumes the 
                  wind farm has the capability to maintain unity power factor at the collector bus of the wind farm.  
                  Potential network impacts were as follows: 
                   
                  Generator Deliverability 
                  (Single or N-1 contingencies for the Capacity portion only of the interconnection) 
                  None 
                   
                  Multiple Facility Contingency 
                  (Double Circuit Tower Line, Line with Failed Breaker and Bus Fault contingencies for the full 
                  energy output) 
                  None 
                            
                  Short Circuit 
                  (Summary form of Cost allocation for breakers will be inserted here if any) 
                   
                  Contribution to Previously Identified Overloads 
                  (This  project  contributes  to  the  following  contingency  overloads,  i.e.  "Network  Impacts", 
                  identified for earlier generation or transmission interconnection projects in the PJM Queue) 
                  None 
                   
                  Steady-State Voltage Requirements 
                  (Results of the steady-state voltage studies should be inserted here) 
                  None 
                  Stability and Reactive Power Requirement for Low Voltage Ride Through 
                  (Results of the dynamic studies should be inserted here) 
                  To be determined. 
                   
                  New System Reinforcements 
                  (Upgrades  required  to  mitigate  reliability  criteria  violations,  i.e.  Network  Impacts,  initially 
                  caused by the addition of this project generation) 
                  None 
                  Contribution to Previously Identified System Reinforcements 
                  (Overloads initially caused by prior Queue positions with additional contribution to overloading 
                  by this project. This project may have a % allocation cost responsibility which will be calculated 
                  and reported for the Impact Study) 
                  © PJM Interconnection 2012.  All rights reserved.    3                             PJMDOCS-# 691313v1 
                                                                                            Q55 System Impact Study Report 
                   
                   
                                                                                                                                                                              
                  (Summary form of Cost allocation for transmission lines and transformers will be inserted here if 
                  any) 
                   
                  None 
                   
                  Potential Congestion Issues 
                   
                  There are several wind generation plants proposed in the general area of the #Q55 project, each 
                  with only 20% of their peak output level considered as a Capacity Resource, and the remaining 
                  80% as an energy only resource.  If all of the wind generation plants are at their maximum output 
                  level simultaneously, a significant number of the transmission facilities, and many underlying 
                  system facilities are likely to be overloaded, restricting operation to a lower output level.  
                  PJM  and  the  Transmission  owner(s)  studied  the  delivery  of  the  energy  portion  of  this 
                  interconnection  request.    The  following  analysis  has  been  performed  to  inform  the 
                  Interconnection  Customer  (Queue/Queues  P&Q)  of  potential  congestion  issues  (operational 
                  restrictions) that may occur and affect the #Q55 project’s ability to operate at full output for 
                  certain system conditions.  The upgrades listed below are not required reliability upgrades for the 
                  Queue #Q55 interconnection.    Please  note  that  the  number  of  facilities  identified  below  as 
                  requiring  upgrades  is  (may  be)  quite  extensive  with  a  number  of  these  facilities  requiring 
                  reconductoring/rebuilding of transmission lines.  Some of the reconductoring/rebuilding projects 
                  can be done in a short time frame while others are quite extensive and will require a long time to 
                  complete.  In general, the time necessary to design and rebuild an extensive facility upgrade will 
                  take  approximately  2-3  years  to  complete.    If  the  #Q55  Interconnection  Customer  wants  to 
                  pursue construction of any of these upgrades, a separate Transmission Interconnection request 
                  must be submitted and the upgrades must be performed as merchant transmission projects.  
                   
                  Delivery of Energy Portion of Interconnection Request 
                   
                  PJM  also  studied  the  delivery  of  the  energy  portion  of  this  interconnection  request.    Any 
                  problems identified below are likely to result in operational restrictions to the project under 
                  study.  The developer can proceed with network upgrades to eliminate the operational restriction 
                  at their discretion by submitting a Merchant Transmission Interconnection request. 
                  Note: Only the most severely overloaded conditions are listed below. Thereis no guarantee of 
                  full delivery of energy for this project by fixing only the conditions listed in this section. With a 
                  Transmission  Interconnection  the  conditions  listed  in  this  section.  With  a  Transmission 
                  Interconnection Request, a subsequent analysis will be performed  which shall study all overload 
                  conditions associated with the overloaded element(s) identified.  
                       1.  The South Bend – Keystone 500kV line (from bus 20118 to bus 11 ckt 1) loads from 
                           101.0% to 101.7% (AC power flow) of its emergency rating (2595MVA) for the single 
                           line contingency outage (AP132). This project contributes approximately 11.4MW to the 
                           thermal congestion.  
                           CONTINGENCY AP132 
                             DISCONNECT BRANCH FROM BUS 20104 TO BUS 20115 CKT 1         /* CABOT 
                           WYLIE RIDGE 500 500 
                           END 
                  © PJM Interconnection 2012.  All rights reserved.    4                             PJMDOCS-# 691313v1 
                                                                                            Q55 System Impact Study Report 
                   
The words contained in this file might help you see if this file matches what you are looking for:

...Generation interconnection pjm impact study report revised for request queue position q snowy creek kv project march all rights reserved pjmdocs v system introduction this provides the documentation of an assessment that has been performed by l c and firstenergy fe in response to a made aes wind llc connection mw capacity farm monpower transmission proposed commercial operation date june facility as per process was accomplished evaluating reliability facilities on interconnected performance power flow ensuring compliance with nerc reliabilityfirst standards identifying reinforcements will need be installed coordinating cooperating staff participating meetings issuing part performing steady state short circuit dynamics necessary conducting studies accordance manuals requirements connected guide planning protocol submitted agreement single line diagram identifies its plan construct turbine property preston county west virginia is approximately miles from substation reduced size total cap...

no reviews yet
Please Login to review.