construction methodology and phasing management plan project opera limerick city county council march 2019 project opera construction methodology and phasing management plan project opera construction methodology and phasing management plan ...

icon picture PDF Filetype PDF | Posted on 13 Sep 2022 | 3 years ago
Partial capture of text on file.
       Construction Methodology
       and Phasing Management
       Plan
       Project Opera
       Limerick City & County Council
       March 2019
           Project Opera – Construction Methodology and
           Phasing Management Plan
              Project Opera – Construction Methodology and
              Phasing Management Plan
              Prepared for:
              Limerick City & County Council
              © 2019 AECOM Ireland Limited. All Rights Reserved.
              This document has been prepared by AECOM Ireland Limited (“AECOM”) for sole use of our client (the “Client”)
              in accordance with generally accepted consultancy principles, the budget for fees and the terms of reference
              agreed between AECOM and Limerick 2030. Any information provided by third parties and referred to herein has
              not been checked or verified by AECOM, unless otherwise expressly stated in the document. No third party may
              rely upon this document without the prior and express written agreement of AECOM.
           Project Opera – Construction Methodology and
           Phasing Management Plan
           Table of Contents
           1.  Introduction ............................................................................................................................................ 5
               1.1 Purpose of this document ............................................................................................................ 5
           2.  Overview of the Proposed Development ................................................................................................. 5
               2.1 The Proposed Development ............................................................................................................. 6
           3.  Site Working Hours ................................................................................................................................ 7
           4.  Legal and Other Requirements ............................................................................................................... 7
               4.1.1 Site Compound/Office location ..................................................................................................... 8
               4.1.2 Control of Documents and Records .............................................................................................. 8
           5.  Construction Phasing ............................................................................................................................. 8
               5.1 Sequence of Works ..................................................................................................................... 8
               5.2 Phasing of the Construction Works .............................................................................................. 9
               5.2.1 Enabling works ............................................................................................................................ 9
               5.2.2 Basement Construction ............................................................................................................. 10
               5.2.3 Temporary Earthworks Support .................................................................................................. 10
               5.3 Permanent Basement Construction ............................................................................................ 11
               5.3.1 New Build Structures ................................................................................................................. 11
           6.  Sensitive receptors on site.................................................................................................................... 13
               6.1 Conservation work to the existing structures ............................................................................... 14
               6.1.1 Monitoring of Existing and Neighbouring Structures .................................................................... 14
               6.1.2 Vibration Monitoring................................................................................................................... 15
               6.1.3 Noise Monitoring ....................................................................................................................... 16
               6.1.4 Dust Monitoring ......................................................................................................................... 16
               6.1.5 Dust management and suppression ........................................................................................... 17
               6.1.6 Construction Workers on Site..................................................................................................... 17
               6.1.7 Construction Vehicles ................................................................................................................ 17
               6.1.8 Discharge licences .................................................................................................................... 18
               6.1.9 Community Liaison .................................................................................................................... 18
               6.1.10 Health and Safety ...................................................................................................................... 18
           7.  Environmental Auditing ......................................................................................................................... 19
           8.  Demolition of Existing Structures .......................................................................................................... 19
               8.1 Isolation from Retained Structures ............................................................................................. 19
               8.2 Weathering of Exposed Gables .................................................................................................. 19
               8.3 Disposal of Demolition Material .................................................................................................. 19
               8.3.1 Use of hoarding ......................................................................................................................... 19
               8.3.2 Construction hours compliance .................................................................................................. 19
               8.3.3 Covered Vehicles ...................................................................................................................... 19
               8.4 Further Mitigation Measures ...................................................................................................... 19
           Appendix A Example List of Relevant Guidance
               Policy & Guidance
           Appendix B Environmental Risk Assessment
           Appendix C List of Mitigation
           Appendix D Ecology Figures referenced in Mitigation and Monitoring Table
The words contained in this file might help you see if this file matches what you are looking for:

...Construction methodology and phasing management plan project opera limerick city county council march prepared for aecom ireland limited all rights reserved this document has been by sole use of our client the in accordance with generally accepted consultancy principles budget fees terms reference agreed between any information provided third parties referred to herein not checked or verified unless otherwise expressly stated no party may rely upon without prior express written agreement table contents introduction purpose overview proposed development site working hours legal other requirements compound office location control documents records sequence works enabling basement temporary earthworks support permanent new build structures sensitive receptors on conservation work existing monitoring neighbouring vibration noise dust suppression workers vehicles discharge licences community liaison health safety environmental auditing demolition isolation from retained weathering exposed g...