effective production rate estimation using construction daily work report data fhwa mt 19 001 9344 504 final report prepared for the state of montana department of transportation in cooperation with ...

icon picture PDF Filetype PDF | Posted on 13 Sep 2022 | 3 years ago
Partial capture of text on file.
                  EFFECTIVE PRODUCTION RATE 
                  ESTIMATION USING CONSTRUCTION DAILY 
                  WORK REPORT DATA
                  FHWA/MT-19-001/9344-504  Final Report
                  prepared for
                  THE STATE OF MONTANA
                  DEPARTMENT OF TRANSPORTATION
                  in cooperation with
                  THE U.S. DEPARTMENT OF TRANSPORTATION
                  FEDERAL HIGHWAY ADMINISTRATION
                                          January 2019
                  prepared by
                  H.David Jeong, Ph.D.
                  Chau Le
                  Vijay Devaguptapu
                  Institute for Transportation
                  Iowa State University
                  Ames, IA
                  RESEARCH PROGRAMS
         
         
         
         
         
         
         
         
         
         
         
         
         
         
         
         
         
         
         
         
         
         
         
         
         
         
         
         
         
         
         
         
         
         
     You are free to copy, distribute, display, and perform the work; make derivative works; 
     make commercial use of the work under the condition that you give the original author 
      and sponsor credit.  For any reuse or distribution, you must make clear to others the 
     license terms of this work.  Any of these conditions can be waived if you get permission 
      from the sponsor.  Your fair use and other rights are in no way affected by the above. 
                                   
                                                 
                                   
            Effective Production Rate 
                    Estimation Using 
             Construction Daily Work 
                        Report Data  
                                   
                      Phase I Report 
                                   
                                    
         Effective Production Rate Estimation Using Construction Daily Work Report Data  
                       Phase I Report 
                           
                           
                     Principal Investigator 
                      Dr. H. David Jeong 
                        Professor 
                Center for Transportation Research and Education,  
                     Institute for Transportation 
                      Iowa State University 
                           
                           
                       Chau Le, and 
                      Vijay Devaguptapu 
                    Graduate Research Assistants 
                           
                           
                           
                           
                           
                           
                       Sponsored by 
                  Montana Department of Transportation 
                            
                           
                           
                           
                            
                           
                           
                           
                           
                       A report from 
                    Institute for Transportation 
                     Iowa State University 
                   2711 South Loop Drive, Suite 4700 
                      Ames, IA 50010-8664 
                      Phone: 515-294-8103 
                      Fax: 515-294-0467 
                     www.intrans.iastate.edu 
         
                   
The words contained in this file might help you see if this file matches what you are looking for:

...Effective production rate estimation using construction daily work report data fhwa mt final prepared for the state of montana department transportation in cooperation with u s federal highway administration january by h david jeong ph d chau le vijay devaguptapu institute iowa university ames ia research programs you are free to copy distribute display and perform make derivative works commercial use under condition that give original author sponsor credit any reuse or distribution must clear others license terms this these conditions can be waived if get permission from your fair other rights no way affected above phase i principal investigator dr professor center education graduate assistants sponsored a south loop drive suite phone fax www intrans iastate edu...

no reviews yet
Please Login to review.