                                               CHAPTER - VIII 
                    CONSTRUCTION PROGRAMME, MANPOWER 
                            DEPLOYMENT & PLANT PLANNING 
                  8.1       General 
                            This  chapter  describes  the  construction  methodology  and 
                  equipment planning for construction of the main components of the project.  
                  The construction methodology for each type of structure has been described 
                  under the relevant sub sections of this chapter. The type and sizes of the 
                  equipment  to  be  used  have  also  been  indicated  while  describing  the 
                  construction  methodology.  The  number  of  machines  required  for 
                  construction of each component of the project has been worked out and total 
                  requirement for each type and size of the major equipment has been arrived 
                  after preparing the construction/ deployment schedule for main components 
                  of the project. In case, the work is executed through award of contract, the 
                  contractors in all probability may suggest their own construction techniques 
                  and  equipment  for  execution  of  the  job  based  on  equipment  actually 
                  available with them. The tentative requirement of machines as worked out 
                  herein  will  help  in  analysis  of  rates  of  works,  cost  estimation  and  in 
                  evaluating  the  reasonableness  of  the  participating  bidders’  construction 
                  techniques  and  equipment,  within  overall  construction  schedule  and  cost 
                  estimate. 
                  8.2       Main project components 
                            An earth fill cum concrete barrage across river Burhi Gandak near 
                  Muriaro village in Samastipur district with pond level  of 49.0 m and crest 
                  level 35 m has been proposed to be constructed. 
                   
                                                          167 
                   
                8.2.1 Salient features of the project 
                1.0   Headworks 
                Burhi Gandak Barrage                                      
                 (i)  Location                                           Near village Muriaro in 
                                                                         Samastipur  district 
                                                                            0 
                       Latitude                                          25 49′35"N 
                                                                            0 
                       Longitude                                         85 53′45" E 
                (ii)  Hydrology                                           
                                Total catchment area                     12,500 sq km 
                                           (a) In India                  10,150 sq km 
                                           (b) In Nepal                  2,350 sq km 
                                 Mean annual rainfall                    1,300  mm 
                Estimated flood discharge                                4920 cumec 
                considering 50 years’                                     
                 return period  at Sikandarpur                            
                G&D site                                                  
                Designed discharge                                       4920 cumec 
                (iii) Pandage                                             
                       Pond level of barrage                             49. 0 m 
                       Sill level of barrage                             35 m 
                (iv) Barrage                                              
                    Type of  barrage                                      Earth fill cum concrete 
                    Top of   barrage                                     54  m 
                    Total length of  barrage                             611 m 
                   Gates                                                  
                      Number                                               16  
                      Size                                               8 m x12.8 m  
                      Type                                               Radial    
                    Height of barrage above the bed level                16 m 
                    Height of barrage  above deepest                     36 m 
                foundation level          
                (v) Undersluice                                           
                        (a)  Length of waterway                           28 m 
                        (b)  Gates                                         
                              Number                                       3  
                              Size                                         8 m x 14 m 
                              type                                         Radial          
                        (c)  Design flood                                4920 cumec 
                                                           168 
                 
                   2.0 Link canal                                             
                             (a) Length of canal                             28.95km 
                             (b) Flow                                        By gravity 
                             (c) Lining                                            Lined 
                             (d) Full supply level                            
                                 (i)  At offtake point                       47.50 m 
                                    (ii) At outfall point                    44.655 m 
                            (e) Full supply depth                            5 m 
                           (f) Bed width                                      
                                (i)  At offtake point                        82.10 m 
                                (ii)  At outfall point                       94.30 m 
                          (g) Side slope                                     1.1:5 
                          (h) Bed slope                                      1:20,000 
                           (i) Design discharge                              492  cumec 
                    
                   8.3         Basis for study 
                   8.3.1       General 
                               Methodology  adopted  for  construction  of  Burhi-Gandak-Noon-
                   Baya-Ganga  link  Project  keeping  in  view    the  proposed  construction 
                   schedule, the compatibility of the construction equipments to site conditions 
                   and the quantities as well as the utilization factor of the equipments within 
                   the scheduled construction period has been described in the foregoing paras 
                   . Number of machines required for construction of each component of the 
                   project has been worked out and the total requirement for each type and size 
                   of machine for the project as a whole has been arrived at after drawing up 
                   the  construction/deployment  schedule  for  the  main  components  of  the 
                   project. 
                               Mechanized construction has been planned for almost all types of 
                   construction jobs so as to achieve consistent quality at a faster rate and also 
                   to minimize the requirement of skilled manpower.   
                               Sequencing of construction activities, wherever possible, has been 
                   attempted in such a way that equipment from one activity, on its completion 
                   can be shifted to the other.  This way, the total requirement of equipment at 
                   a time would be reduced and also, sufficient utilization of equipment on the 
                   project would be ensured. 
                    
                                                               169 
                    
               8.3.2      Construction material sources 
                          Locations of different borrow areas and quarries for construction 
               materials  have  been  described  in  the  Chapter  II  viz.  “Survey  and 
               Investigation”. 
               8.3.3      Basic considerations 
                          Based on past experience, about 8 working months in a year are 
               available  in  the  area  where  the  project  is  situated.  All  the  works  are 
               proposed to be executed in two shifts.   
               8.3.3.1    Scheduled working hours 
                          The requirement of equipments has been planned in reference to 
               the “Guidelines for preparation of Detailed Project Report of Irrigation and 
               Multipurpose  Projects,    MoWR,  Govt  of  India,2010.  Requirement  of 
               equipments is based on the number of working days available, which further 
               depends upon climatic conditions of the project area. In the project area, the 
               monsoon sets in during June and continues till October in the project area.  
               For equipment planning purpose the monsoon season has been considered 
               from 15th June to 15th October.   
                          As per the standard guidelines, the following assumptions have 
               been made to work out the scheduled working hours considering 25 working 
               days per month  
                          Accordingly, schedule working hours in a year with 200 available 
               working days should be taken as given in Table 8.1 
                                                    Table-8.1 
                     Type of shift                          Schedule working hours 
                    Single shift work/day                      1200 Hrs (8x25x6)  
                    Two shift work/day                         2000 Hrs (8x25x10) 
                    Three shift work/day                       2500 Hrs (8x25x12.5) 
                
                          Two shifts  working  of  equipment  is  normally  considered  most 
               economical in view of the high cost of three shift working on account of low 
               availability of equipment and higher stand-by equipment requirement. Thus 
               planning for  construction  of  all  the  components  of  Burhi  Gandak-Noon-
               Baya Ganga link canal project works have been carried out based on two 
               shifts per day working.  
                                                        170 
                
The words contained in this file might help you see if this file matches what you are looking for:

...Chapter viii construction programme manpower deployment plant planning general this describes the methodology and equipment for of main components project each type structure has been described under relevant sub sections sizes to be used have also indicated while describing number machines required component worked out total requirement size major arrived after preparing schedule in case work is executed through award contract contractors all probability may suggest their own techniques execution job based on actually available with them tentative as herein will help analysis rates works cost estimation evaluating reasonableness participating bidders within overall estimate an earth fill cum concrete barrage across river burhi gandak near muriaro village samastipur district pond level m crest proposed constructed salient features headworks i location latitude n longitude e ii hydrology catchment area sq km a india b nepal mean annual rainfall mm estimated flood discharge cumec conside...

no reviews yet
Please Login to review.