Generic Tree of Ground Segment Documents
PV, 7 Nov 2007
Documents Responsibility Date 1st agreed issue Comments
Mission Requirements Document (MRD) Project Programme Proposal scientific requirements for the mission
Satellite System Requirements Document (SRD) Project Phase B/C/D ITT satellite spec (+ attachments such as deliverable items and docs)
Memorandum Of Understanding(s) with External Partner(s) (if any) Project SAT-PDR definition of relationship and respective duties of ESA and partner
Data Policy Project Phase B/C/D ITT normally defined for a programme, may be amended per mission
Context Project Master Schedule Project adhoc updated regularly, includes space and ground segments
Ground Segment Functional and Operational Concept Project GS-RR functional breakdown, operations concept, high-level system requirements
Ground Segment Implementation Plan Project GS-RR implementation overview, responsibilities, reviews, GS schedule
Ground Segment Technical Budget Project GS-PDR performance figures for network links, run-time processing, storage, distribution…
Mission Analysis Studies Document Project adhoc agreed results on orbit, instrument planning, downlinks, etc… (refs to detailed TNs)
FOS Mission Implementation Requirements Document (MIRD) Project GS-RR tasks, deliverables, CFIs, high-level requirements
FOS Mission Implementation Plan (MIP) Esoc GS-RR architecture, internal interfaces, ops concept, detailed schedule, manpower, dev plan
Functional FOS Facilities SRDs Esoc GS-PDR specs of sub-systems, for information to Project
Specs PDGS Mission Implementation Requirements Document (MIRD) Project GS-RR tasks, deliverables, CFIs, high-level requirements
PDGS Mission Implementation Plan (MIP) Esrin GS-RR architecture, internal interfaces, teams, detailed schedule, manpower, dev plan
PDGS Facilities SRDs Esrin GS-PDR specs of sub-systems, for information to Project
Ground Segment Interfaces Overview Project GS-PDR systematic structured list of all interfaces, ICDs, format specs; used to conf control interfaces
ICDs
Space2Ground ICDs Sat Prime SAT-PDR RF and data interfaces, for command/control and science data
Ground Segment ICDs Project/Esrin/Esoc GS-CDR interfaces between Satellite, FOS, PDGS and external systems (if any)
Format Specifications
Tailorisation of EO File Format Standards Project/Esrin GS-RR file naming conventions, etc… (closing the issues left open by the Standard)
Packet Utilisation Standard (PUS) Sat Prime SAT-PDR TM/TC definition, VCID and APID allocation, services definition, etc...
Interfaces TM/TC Format Specifications Sat Prime SAT-PDR detailed definition of packets and fields
Specs Data Products Specifications Project/Esrin SAT-PDR (L0); GS-CDR (L1/L2) detailed definition of science data products
Other File Format Specifications Project/Esrin GS-CDR detailed definition of other files (e.g. auxiliary data)
Inputs to Operations
Satellite TM/TC Database ICD Esoc SAT-PDR spec of SDB delivery format (typically SCOS2K format)
OBSW Images ICD Esoc SAT-PDR spec of OBSW delivery format
Satellite Flight Operations Manual (FOM) Sat Prime SAT-CDR detailed description of satellite operations, including flight dynamics constraints
Instrument Operations Manual(S) (IOM(s)) Sat Prime SAT-CDR detailed description of instruments operations
Flight Operations Procedures (FOP) Sat Prime SAT-CDR flight procedures, tested on satellite (typically in MOIS format)
Satellite documents
Satellite Assembly Integration and Validation (AIV) Plan/Test Specs Sat Prime SAT-PDR overall plan for satellie integration and validation
Satellite AIV Procedures Sat Prime adhoc detailed testing procedures
Satellite AIV Reports Sat Prime adhoc detailed test reports
Satellite Requirements Traceability Matrix Sat Prime SAT-QR systematic verification of SRD requirements
FOS documents
FOS Validation Plan/Test Specs Esoc GS-CDR overall plan for FOS integration and validation
FOS Acceptance Procedures Esoc adhoc detailed testing procedures (FOS overall and FOS facilities)
FOS Acceptance Reports Esoc adhoc detailed test reports (FOS overall and FOS facilities)
FOS Requirements Traceability Matrix Esoc GS-AR systematic verification of MIRD requirements
PDGS documents
PDGS Validation Plan/Test Specs Esrin GS-CDR overall plan for PDGS integration and validation
Validation
PDGS Acceptance Procedures Esrin adhoc detailed testing procedures (PDGS overall and FOS facilities)
Validation
PDGS Acceptance Reports Esrin adhoc detailed test reports (PDGS overall and FOS facilities)
PDGS Requirements Traceability Matrix Esrin GS-AR systematic verification of MIRD requirements
System documents
Overall System Validation Plan Project GS-PDR systematic list of tests, clarifies SVT / GSOV / S2G tests coverage/responsabilities, test scenario, test data preparation responsibilities
SVT Plan Project/Esoc SAT-CDR overall plan for SVTs (today called SVT Master Test Plan)
SVT Test Plan/Procedures Project/Esoc adhoc detailed plans/procedures for each SVT
SVT Test reports Project/Esoc adhoc detailed reports for each SVT
GSV Plan Project GS-CDR was "GSOV": tests of all ground links: compatibility, integration, validation
GSV Test Plan/Procedures Project adhoc detailed plans/procedures for each GSV test
GSV Test Reports Project adhoc detailed reports for each GSV test
Space2Ground (S2G) Plan Project SAT-CDR "everything else": RF tests, X-band compatibility tests, etc…
S2G Test Plan/Procedures Project adhoc detailed plans/procedures for each S2G test
S2G Test Reports Project adhoc detailed reports for each S2G test
high-level plans
Calibration Plan Project SAT-CDR plan of instruments and platform calibration activities, during phases E1 and E2
Validation Plan Project/Esrin GS-CDR plan of instruments and platform validation activities, during phases E1 and E2
OBSW Maintenance Plan Project/Sat Prime SAT-CDR definition of tasks and responsabilities for OBSW maintenance and validation
training
FOS Training Plans Esoc GS-CDR simulations, other training, mission readiness
FOS Training Reports Esoc GS-AR detailed reports on training
PDGS Training Plans Esrin GS-CDR facilities and system-level training
PDGS Training Reports Esrin GS-AR detailed reports on training
user manuals
FOS Facilities User Manuals Esoc GS-AR detailed operating manuals for each facility
PDGS Facilities User Manuals Esrin GS-AR detailed operating manuals for each facility
Operations Plan for Phase E1 Project GS-CDR covers LEOP, IOV, CalVal at system level
FOS documents
FOS Operations Plan for LEOP Esoc GS-AR for LEOP, Esoc control of Operations
FOS Facilities Operations Procedures for LEOP Esoc GS-AR detailed procedures
Operations FOS Operations Plan for In-Orbit Verification (IOV) Esoc GS-AR for IOV, Project control of Operations
FOS Facilities Operations Procedures for IOV Esoc GS-AR detailed procedures
FOS Operations Plan for CalVal Esoc GS-AR for CalVal during phase E1, Project control of Operations
FOS Facilities Operations Procedures for CalVal Esoc GS-AR detailed procedures
PDGS documents
PDGS Operations Plan for IOV Esrin GS-AR for IOV, Project control of Operations
PDGS Facilities Operations Procedures for IOV Esrin GS-AR detailed procedures
PDGS Operations Plan for CalVal Esrin GS-AR for CalVal during phase E1, Project control of Operations
PDGS Facilities Operations Procedures for CalVal Esrin GS-AR detailed procedures
Operations Plan for Phase E2 Esrin GS-CDR covers routine operations at system level
FOS documents
FOS Operations Plan for Phase E2 Esoc GS-AR for routine ops and CalVal during phase E2, Esrin control of Operations
FOS Facilities Operations Procedures for Phase E2 Esoc GS-AR detailed procedures
PDGS documents
PDGS Operations Plan for Phase E2 Esrin GS-AR for routine ops and CalVal during phase E2, Esrin control of Operations
PDGS Facilities Operations Procedures for Phase E2 Esrin GS-AR detailed procedures
Plan for Transfer to Phase E2 Project/Esrin GS-AR transfer of responsibility between Project and Esrin