jagomart
digital resources
picture1_Powerpoint Iso 64883 | A05 Mc 2021 12 07 09 Cpv Presentation


 113x       Tipe PPTX       Ukuran file 0.69 MB       Source: www.iso-ne.com


Powerpoint Iso 64883 | A05 Mc 2021 12 07 09 Cpv Presentation

icon picture PPTX Power Point PPTX | Diposting 26 Aug 2022 | 3 thn lalu
Berikut sebagian tangkapan teks file ini.
Geser ke kiri pada layar.
     FA Improvement Process
     •  CPV has identified the need to reform the current non-commercial financial 
        assurance construct based upon recent experience with delayed and failed 
        projects that have participated in the last six Forward Capacity Auctions.
     •  ISO/NEPOOL made FA revisions following experience with a failed project from 
        FCA 10 by implementing the Trading FA provisions and cover requirements.
     •  ISO filed on November 4 with FERC to terminate another significant non-
        commercial capacity resource for FCA 16 that failed to advance a project 
        development, after it had participated in three consecutive Forward Capacity 
        Auctions: FCA 13-15. 
      
     •  Further evidence that existing financial/markets consequences remain insufficient 
        to appropriately self-discipline behavior for sponsors of a failed project 
        participating in the auctions.
                                                                                                      2
        Problem Statement
     •   Existing FA requirements are insufficient to deter non-commercial capacity from 
         participating in subsequent capacity auctions for highly unlikely projects.
          •   The current FA design attempts to balance keeping financial barriers to entrance low (low initial FA) 
              against the need to ensure delivery of physical capacity through the use of a physical milestone tracking 
              process.
     •   The current FA design makes no distinction between a project meeting all its 
         milestone commitments, a delayed project, and a totally failed project.
          •   There is no performance-based consequence across the range of performance.
     •   Failed non-commercial capacity participating in capacity auctions financially impact 
         all other capacity sellers in the auction with no recourse by those impacted.
          •   Financial impacts to other CSO holders is through lower clearing prices in each auction and higher 
              performance risk.
     •   The qualification process and the Financial Assurance requirements are not 
         working together to ensure that cleared projects are “real” or “timely.”
          •   No workable relationship between the two mechanisms.
                                                                                                                           3
      
       Impacts from the Problems
     • A resource that has not achieved COD by its FCA required commitment date will 
       have posted just three months of FA but would have participated in four FCAs.
        •  And if not terminated by ISO, could continue to impact future FCAs.
     • The amount of FA required as projects begin to fail does not reflect the harm to the 
       market nor properly incent action on the part of the project developer.
        •  Killingly’s market impact is in the realm of $380 million over three auctions: $0.31 kw-month average.
     • The opportunity to recover previously posted FA incents resources to stick around.
        •  There are minimal consequences for any delays by the project, and potential upside through return of 
           trading FA.
            •  The only real tool in the ISO toolbox is a sledgehammer - termination.
     • The only performance-based FA is after the resource has failed to meet its initial 
       COD.
        •  And even this does not consider the status of the project (i.e.: has it even started construction?).
                                                                                                  4
       Current Milestone Schedule 
     •  The current Critical Path Milestone Schedule process requires all non-commercial capacity to 
        provide a schedule for major milestones as part of its qualification.
             III.13.1.1.2.2.2. Critical Path Schedule. In the New Capacity Qualification Package, the Project Sponsor must provide a critical path 
             schedule for the project with sufficient detail to allow the ISO to evaluate the feasibility of the project being built and the feasibility that 
             the project will meet the requirement that the project achieve all its critical path schedule milestones no later than the start of the 
             relevant Capacity Commitment Period. 
     •  A critical path schedule report is due on a quarterly basis from the Project Sponsor.
         •  Each report must update the original schedule, note changes to milestones and project scope. (III. 13.2.2.1)
         •  Achievement of milestones must include documentation in support.
             •   Failure to provide the report can result in termination.
     •  Failure to meet the original milestone, and changes to the schedule, may result in a monthly 
        reporting requirement (III.13.3.3).
         •  Covering obligations for late delivery is optional…
             •    Although choosing not to cover will result in failure to cover charge, but only after the start of the delivery period 
                 (III.13.3.4.(b)).
             •   Failure to provide  the monthly reports can result in termination.
     •  There are no financial consequences of failing to achieve milestones until after the delivery 
        date has been passed.                                                                                  5
       Proposed FA Enhancements
     Current FA includes:
     •  Base FA:  FA that is collected prior to the primary FCA and then prior to the first 
        and second subsequent auctions.
     •  Trading FA:  FA that is collected in the delivery period as any positive trading 
        revenue from cover transactions. 
     This proposal is to establish two new categories of FA and enhance the existing 
     design– changes effective only with failure to perform consistent with FCA 
     commitments:
     •  Milestone FA:  New FA requirements for projects that fail to meet their pre-COD 
        delivery obligations.
     •  Delay FA:  Enhanced FA requirements for project that fail to deliver physical 
        obligations at their commitment date.
     •  Adding FA prior to third subsequent FA for significantly delayed projects
                                                                                                     6
Kata-kata yang terdapat di dalam file ini mungkin membantu anda melihat apakah file ini sesuai dengan yang dicari :

...Fa improvement process cpv has identified the need to reform current non commercial financial assurance construct based upon recent experience with delayed and failed projects that have participated in last six forward capacity auctions iso nepool made revisions following a project from fca by implementing trading provisions cover requirements filed on november ferc terminate another significant resource for advance development after it had three consecutive further evidence existing markets consequences remain insufficient appropriately self discipline behavior sponsors of participating problem statement are deter subsequent highly unlikely design attempts balance keeping barriers entrance low initial against ensure delivery physical through use milestone tracking makes no distinction between meeting all its commitments totally there is performance consequence across range financially impact other sellers auction recourse those impacted impacts cso holders lower clearing prices each h...

no reviews yet
Please Login to review.