Outline Construction Environmental
Management Plan (CEMP)
Celbridge Pedestrian & Cycle Bridge
Client: National Transport Authority
Date: February 2022
Job Number: 17_190A
Clifton Scannell Emerson Associates Limited,
Consulting Engineers, Seafort Lodge, Castledawson Avenue, Blackrock, Co. Dublin, Ireland.
T. +353 1 2885006 F. +353 1 2833466 E. info@csea.ie W. www.csea.ie
Document Control Sheet
Project Name: Celbridge Pedestrian & Cycle Bridge
Project Number: 17_190A
Report Title: Outline Construction Environmental Management Plan
Filename: RPT-17_190A-003
Issue No. Issue Status Date Prepared by Checked by
st
1 DRAFT 02-03-2021 NM CB
nd
2 DRAFT 13-01-2022 CAB GE
rd
3 FINAL 15-02-2022 CAB GE
Project Number: 17_190A
Project: Celbridge Pedestrian & Cycle Bridge
Title: Outline Construction Environmental Management Plan (OCEMP)
Table of Contents
1 INTRODUCTION .............................................................................................................................. 4
1.1 BACKGROUND ................................................................................................................... 4
1.2 SITE LOCATION ................................................................................................................. 4
1.3 SCOPE OF WORKS ........................................................................................................... 5
2 DESCRIPTION OF THE PROPOSED DEVELOPMENT................................................................. 6
2.1 PROJECT DESCRIPTION .................................................................................................. 6
2.2 CONSTRUCTION METHODOLOGY AND PROGRAMME ................................................ 8
3 CONSTRUCTION ENVIRONMENTAL MANAGEMENT PLAN (CEMP) ....................................... 11
3.1 CEMP Contents ................................................................................................................. 11
3.2 ENVIRONMENTAL POLICY ............................................................................................. 11
3.3 ENVIRONMENTAL REGISTER ........................................................................................ 12
3.4 PROJECT ORGANISATION AND RESPONSIBILITY ...................................................... 12
3.5 PROJECT COMMUNICATION AND CO-ORDINATION .................................................. 15
3.6 TRAINING ......................................................................................................................... 15
3.7 OPERATIONAL CONTROL .............................................................................................. 16
3.8 CHECKING AND CORRECTIVE ACTION ........................................................................ 16
3.9 ENVIRONMENTAL CONTROL MEASURES.................................................................... 16
3.10 COMPLAINTS PROCEDURE ........................................................................................... 16
3.11 Environmental Emergency Response Plan ....................................................................... 16
3.12 Concrete Control Procedure .............................................................................................. 17
3.13 Fuel and Oil Management Plan ......................................................................................... 17
3.14 Protection of Water Resources ......................................................................................... 17
3.15 Construction Traffic Management Plan ............................................................................. 18
3.16 Management of Excavation and Spoil ............................................................................... 18
3.17 Waste Management Plan .................................................................................................. 19
3.18 Construction Noise Management Plan .............................................................................. 19
3.19 Construction Dust Management Plan ................................................................................ 19
3.20 Materials Handling and Storage Plan ................................................................................ 19
3.21 Monitoring and Auditing Procedure ................................................................................... 20
3.22 Environmental Accidents, Incidents and Corrective Actions Procedure ........................... 20
4 ENVIRONMENTAL COMMITMENTS ............................................................................................ 21
4.1 MITIGATION MEASURES ................................................................................................ 21
5 TRAFFIC MANAGEMENT ............................................................................................................. 32
5.1 TRAFFIC MANAGEMENT PLANS .................................................................................... 32
5.2 ENVIRONMENTAL CONTROLS ...................................................................................... 32
5.3 VEHICLE MOVEMENT AND DELIVERIES ...................................................................... 32
5.4 ROAD SAFETY ................................................................................................................. 33
6 SUMMARY ..................................................................................................................................... 35
www.csea.ie Page 3 of 36
Project Number: 17_190A
Project: Celbridge Pedestrian & Cycle Bridge
Title: Outline Construction Environmental Management Plan (OCEMP)
1 INTRODUCTION
1.1 BACKGROUND
1.1.1 Clifton Scannell Emerson Associates (CSEA) have prepared this Outline Construction
Environmental Management Plan (OCEMP) to support to Part 8 planning application for the Celbridge
Pedestrian and Cycle Bridge.
1.1.2 The OCEMP applies to all works associated with the construction of the proposed civil and
structural works including the pre-construction site clearance works. As a contractor has not yet been
appointed, this OCEMP has not been formally adopted and further development and commitment to
the OCEMP will be undertaken following selection of Contractors and before commencement of site
works.
1.1.3 This Outline Construction Environmental Management Plan (OCEMP) sets out the procedures,
standards, work practices and management responsibilities to address potential environmental effects
that may arise from construction of the Proposed Development.
1.1.4 The OCEMP provides the environmental management framework for the appointed Contractors
and Sub Contractors as they incorporate the mitigating principles to ensure that the work is carried out
with minimal impact on the environment. The construction management staff as well as Contractors
and Sub Contractors staff must comply with the requirements and constraints set forth in this OCEMP
in developing their CEMP. The key environmental aspects associated with the construction of the
Celbridge Pedestrian and Cycle Bridge, and the appropriate mitigation and monitoring controls, are
identified in the OCEMP.
1.1.5 The implementation of the requirements of the OCEMP will ensure that the construction phase of
the Proposed Development is carried out in accordance with the commitments made by Kildare
County Council in the planning application process for the Proposed Development, and as required
under the planning approval. Once adopted, the CEMP is considered a living document that will be
updated according to changing circumstances on the Proposed Development and to reflect current
construction activities. The CEMP will be reviewed on an ongoing basis during the construction
process and will include information on the review procedures.
1.16 This document should be read in conjunction with the following documents prepared for the
proposed development:
Ecological Impact Assessment (RPS, 2022);
Archaeological and Built Heritage Assessment Report (John Cronin and Associates, 2022);
and
Landscape and Visual Assessment Report (RPS, 2022).
1.2 SITE LOCATION
1.2.1 The Proposed Development is a pedestrian and cycle bridge on the downstream side of the
existing road bridge in Celbridge town. The Site Location can be seen on Figure 1.1 and Figure 1.2.
www.csea.ie Page 4 of 36