296x Filetype XLSX File size 0.13 MB Source: betterbuildingssolutioncenter.energy.gov
Sheet 1: Project Tracker
Projects Summary | Implementation Summary | ||||||||||||||
Green | Input | ||||||||||||||
Total Savings (USD) | $0.00 | Yellow | Choose from List | Total Projects | 0 | ||||||||||
Total Implementaion Cost (USD) | $0.00 | Pink | Financial Summary | Implemented | 0 | ||||||||||
Total Electricity Savings (kWh) | 0 | Light Blue | Implementation Summary | Funding needed | $- | ||||||||||
Total Natural Gas Savings (MMBtu) | 0 | Orange | Calculated | ||||||||||||
Overall Payback (Years) | or 0.0 months | ||||||||||||||
Sr. | Project Details | Status | Savings | ||||||||||||
Tracking ID | Project Description | Plant | Division | Business | Owner | Energy System | Annual Savings Estimate | Project Origin | Funding Status | Implementation Cost | Implementation Status | Date Completed | Electricity Savings | Natural Gas Savings | |
(mm/yyyy) | kWh | MMBtu | |||||||||||||
Projects Summary | Implementation Summary | ||||||||||||||
Green | Input | ||||||||||||||
Total Savings (USD) | $77,100.00 | Yellow | Choose from List | Total Projects | 6 | ||||||||||
Total Implementaion Cost (USD) | $56,000.00 | Pink | Financial Summary | Implemented | 3 | ||||||||||
Total Electricity Savings (kWh) | 1,773,300 | Light Blue | Implementation Summary | Funding needed | $48,000.00 | ||||||||||
Total Natural Gas Savings (MMBtu) | 0 | Orange | Calculated | ||||||||||||
Overall Payback (Years) | 0.73 | or 8.7 months | |||||||||||||
Sr. | Project Details | Status | Savings | ||||||||||||
Tracking ID | Project Description | Plant | Division | Business | Owner | Energy System | Annual Savings Estimate | Project Origin | Funding Status | Implementation Cost | Implementation Status | Date Completed | Electricity Savings | Natural Gas Savings | |
(mm/yyyy) | kWh | MMBtu | |||||||||||||
TreasureHunt-01 | Reduce Pressure | Houston-A | Production | Business Type - I | John Smith | Compressed Air | $10,000.00 | Treasure Hunt | Funding Unnecessary (OPEX) | $1,000.00 | Implemented | 05/2021 | 230,000 | 0 | |
TreasureHunt-01 | Fix Leaks | Houston-A | Production | Business Type - I | Jane Doe | Compressed Air | $7,800.00 | Treasure Hunt | Funding Unnecessary (OPEX) | $5,000.00 | Planned | 179,400 | |||
TreasureHunt-01 | Increase storage size | Houston-A | Production | Business Type - I | John Smith | Compressed Air | $9,200.00 | Treasure Hunt | Funding Requested | $25,000.00 | On-hold | 211,600 | |||
TreasureHunt-01 | Change pressure setting on compressor 2 | Houston-A | Production | Business Type - I | John Smith | Compressed Air | $2,600.00 | Treasure Hunt | Funding Unnecessary (OPEX) | $1,000.00 | Implemented | 07/2021 | 59,800 | ||
TreasureHunt-01 | Make compressor 3 the base compressor | Houston-A | Production | Business Type - I | Jane Doe | Compressed Air | $12,500.00 | Treasure Hunt | Funding Unnecessary (OPEX) | $1,000.00 | Implemented | 08/2021 | 287,500 | ||
TreasureHunt-01 | Use machine 2 (newer) instead of production machine 1 to reduce compressed air usage | Houston-A | Production | Business Type - I | Mike Doall | Compressed Air | $35,000.00 | Treasure Hunt | Funding Requested | $23,000.00 | On-hold | 805,000 |