construction st louis villa december2019 january2020 project lead adam smith w49 w50 w51 w52 w1 w2 project budget estimated 325 00000 baseline 300 00000 task costs estimated 318 00000 baseline ...

icon picture XLSX Filetype Excel XLSX | Posted on 14 Aug 2022 | 3 years ago
Partial file snippet.
              Construction - St. Louis Villa                                                                                                                                           December-2019                                                                                                                                    January-2020
                                                                                                                                                                                   ########################################################################################################################
              Project Lead: Adam Smith                                                                                                                                             W49                               W50                               W51                                W52                               W1                                W2
              Project Budget: Estimated: $325,000.00 | Baseline: $300,000.00 | Task Costs: Estimated: $318,000.00 | Baseline: $300,000.00 | Actual: $178,150.00                      2   3    4    5    6    7    8    9   10   11   12   13   14  15   16   17   18   19   20   21   22   23  24   25   26   27   28   29   30   31   1    2    3    4    5   6    7    8    9   10
              WBS Task Name                                               Priority        Resource                Start                 Finish          Duration     Percent 
                                                                                                                                                                    Complete        M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F
              1      Architectural Design                                NORMAL             Adam              Mon 02-Dec-19          Mon 09-Dec-19               6    100%              2,700.00
              1.1       Create draft of architecture                     NORMAL             Adam              Mon 02-Dec-19          Wed 04-Dec-19               3    100%              2,700.00
              1.1.1         Prepare construction documents               NORMAL           Matthew             Mon 02-Dec-19          Wed 04-Dec-19               3    100%              2,700.00
              1.2       Agreement to architectural plan                  NORMAL             Adam               Thu 05-Dec-19            Fri 06-Dec-19            2    100%
              1.3       Sign agreement with Client                         HIGH             Adam              Mon 09-Dec-19          Mon 09-Dec-19               1    100%
              2      Construction Phase                                  NORMAL             Adam               Tue 10-Dec-19          Thu 26-Dec-19             19     70%                                                     201,800.00
              2.1       Foundation                                       NORMAL            Adrian              Tue 10-Dec-19           Tue 17-Dec-19             8    100%                                                     73,800.00
              2.1.1         Excavation                                   NORMAL            Adrian              Tue 10-Dec-19            Fri 13-Dec-19            4    100%                                                     35,000.00
              2.1.2         Pour Concrete                                NORMAL             Danny             Mon 16-Dec-19            Tue 17-Dec-19             2    100%                                                                                  35,000.00
              2.1.3         Level Concrete                               NORMAL             Danny             Mon 16-Dec-19            Tue 17-Dec-19             2    100%                                                                                  3,800.00
              2.2       Ground Floor                                     NORMAL             Gary              Wed 18-Dec-19           Thu 26-Dec-19             11     40%                                                                                            128,000.00
              2.2.1         Walls to 1st Floor                             HIGH             Gary              Wed 18-Dec-19          Mon 23-Dec-19               4     80%                                                                                            65,000.00
              2.2.2         Windows/ Doors                               NORMAL             Gary              Wed 18-Dec-19          Mon 23-Dec-19               4     40%                                                                                            47,000.00
              2.2.3         Roof structure                               NORMAL             Toby               Tue 24-Dec-19          Thu 26-Dec-19              3      0%                                                                                                                         16,000.00
              3      Decoration Phase                                    NORMAL             Toby                Fri 27-Dec-19          Tue 31-Dec-19             6      0%                                                                                                                                       93,500.00
              3.1       Walls and Tiles                                  NORMAL             Gary                Fri 27-Dec-19          Tue 31-Dec-19             3      0%                                                                                                                                       13,500.00
              3.2       Interiors/ Furniture                               LOW               Sara               Fri 27-Dec-19          Tue 31-Dec-19             3      0%                                                                                                                                       80,000.00
              4      Final touches                                       NORMAL             Adam               Wed 01-Jan-20           Thu 02-Jan-20             2      0%                                                                                                                                                               20,000.00
              5      Move in with Family                                 NORMAL             Celine               Fri 03-Jan-20          Fri 03-Jan-20            1      0%
                     Exported from Gantt Excel on 26-Dec-19 
                     23:22:52
                     Note: This is a sample Gantt Chart created in Gantt Excel and exported to XLSX file format
The words contained in this file might help you see if this file matches what you are looking for:

...Construction st louis villa december january project lead adam smith w budget estimated baseline task costs actual wbs name priority resource start finish duration percent complete m t f s architectural design normal mon dec create draft of architecture wed prepare documents matthew agreement to plan thu fri sign with client high phase tue foundation adrian excavation pour concrete danny level ground floor gary walls windows doors roof structure toby decoration and tiles interiors furniture low sara final touches jan move in family celine exported from gantt excel on note this is a sample chart created xlsx file format...

no reviews yet
Please Login to review.