Sheet 1: Construction Gantt Chart
KWA | |||||||||||||||
Project: | JJM -Kannur Dt.Madayi Pt | ||||||||||||||
Construction site: | Madayi Panchayath | ||||||||||||||
Construction Activities | DURATION (Days) |
||||||||||||||
START DATE | END DATE | DESCRIPTION | |||||||||||||
6/10/21 | 7/31/21 | Supply of pipe | 51 | ||||||||||||
6/10/21 | 6/22/21 | earth work of sump at kambipalam | 12 | ||||||||||||
7/1/21 | 7/10/21 | earth work of sump at memala | 9 | ||||||||||||
6/23/21 | 9/24/21 | concrete work of sump at kambipalam | 91 | ||||||||||||
9/25/21 | 12/25/21 | concrete work of sump at memala | 90 | ||||||||||||
9/1/21 | 12/31/21 | pipe laying work | 120 | ||||||||||||
1/1/22 | 2/25/22 | finishing work and tank connections of sump | 54 | ||||||||||||
2/26/22 | 3/15/22 | trial running and commissioning | 19 | ||||||||||||
USEFUL TIPS | |
1 | When enteringactivity start and end dates in columns "C" and "D" use the following date format: DD/MM/YYYY |
2 | To change colour of fill and text in cells, use HOME -> FONT tool palette. |
3 | To change the start date shown on the gantt chart: Fotmat -> (Current Selection tab) Format Selection -> Axis Options -> Bound: Minimum -> Change value to a number that will be appropriate for your project start date. e.g. 43831 = 1/1/2020 44197 = 1/1/2021 44562 = 1/1/2022 ..... |
no reviews yet
Please Login to review.