Sheet 1: Initial Capacity Assessm. Sheet
I. Key Information A) Product | B) Customer Production | ||||||||||
Supplier | Annual quoted volume (RFQ volume) | Method | Date | Description | |||||||
Site Location | Production weeks/year (at customer) | ||||||||||
Parma Code | X Customer Demand / Week | - | |||||||||
Date of Study | |||||||||||
Part # / Name | |||||||||||
II. Capacity Planning | |||||||||||
Operating pattern for the specific part | Process 1 | Process 2 | Process 3 | Process 4 | Process 5 | Process 6 | Process 7 | ||||
Process description | |||||||||||
Dedicated or Shared process (for shared process, show only the operating pattern for the specific part) |
2 | ||||||||||
A | Shifts/day | ||||||||||
B | Total hours/shift | ||||||||||
B1 | Hours/shift used for this part number (shared prod) | ||||||||||
C1 | Personal breaks: lunch, breaks (minutes/shift) | ||||||||||
C2 | Planned Maintenance (minutes/shift) | ||||||||||
D | Days/week | ||||||||||
E | Net available time (production hours/week) [A*(B1-(B1/B)*((C1+C2)/60))*D] |
- | - | - | - | - | - | - | |||
Projected Downtime for this part number | |||||||||||
F | Tool / Variant Changeover (minutes) | ||||||||||
G | Changeovers / shift | ||||||||||
H | Inspections of facilities / shift (minutes) | ||||||||||
I | Breakdowns / shift (unscheduled downtime) (minutes) | ||||||||||
J | Total projected downtime/week (hours) [((FxG+H+I)/60xAxD)*B1/B] | - | - | - | - | - | - | - | |||
K | Equipment Availability [(E-J)/E] | - | - | - | - | - | - | - | |||
Projected Quality Rate (%) | |||||||||||
Projected percent of parts scrapped and/or reworked For linked processes, see notes. |
|||||||||||
L | Projected Quality Rate (%) | - | - | - | - | - | - | - | |||
Planned Cycle time / Capacity | |||||||||||
Required Cycle time needed to cover exact customer demand (sec/part) [E*3600*K*L/ X] | - | - | - | - | - | - | - | ||||
M | Net Planned Ideal Cycle Time (sec/part) For multiple cavities in one tool, see notes. |
||||||||||
Planned production capacity / week [(E-J)*3600*L/M] | - | - | - | - | - | - | - | ||||
0 | DEDICATED | ||||||||||
1 | SHARED |