                                                                                                             Response to RFP Questions
       Question  Company        Solicitation Reference                                    Questions                                                                                Response
       Number
                                                          Can you please post the sign-in sheets from the site visits? Gerald          The list of companies have completed all pre proposal meeting and tour requirements to 
           1       Kitchell           Site Visits         mentioned they would be made available. Thank you.                           further participate in this RFP was uploaded to the AOC website on January 19,2011.
                                                          During the wrap up session immediately following the site tours, AOC 
                                                          stated that contractors should have received a computer disk containing      The CDs referenced during this meeting were provided to all contractors (1 per company) at 
                                Site Tours – Wrap Up      preventive maintenance and work-order data.  Our firm never received 
           2         CBRE         Session (Friday, 14     such a disk.  How do we obtain one?                                          the Pre-Proposal Kick Off meeting on January 5th. There was one set totaling 4 CDs: one with 
                                       January)                                                                                        Exhibits labeled Exhibit J-J7, Exhibit K-K.13, Exhibit L.1-l4, RFP Exhibit Document, Draft - BAS 
                                                                                                                                       Policy Manual.; and three CDs containing the relevant JOC Contracting documents for NCRO, 
                                                                                                                                       BANCRO, and SRO. 
                                                          During the closing session on 14 January, AOC informed contractors that      There may be some misunderstanding. Payments for JOC projects under $100K will be 
                                                          final payment for IDIQ or task order work (< $100K) would only be            invoiced in the month the project is completed.  This could be the same month it was started 
                                                          reimbursed on a semi-annual basis.  Progress payments, we were told,         or several months afterwards.  Payment will be made 60 days after receipt of the invoice.  
                                                          could be negotiated for tasks costing > $100K.  Does AOC accept the          Thus, in some case you may have started the work 6 months before you receive payment.  As 
                                Site Tours – Wrap Up      general approach of including a finance charge within prices negotiated      to finance charges, there will be no specific line item for this.  It is anticipated that it will be 
           3         CBRE         Session (Friday, 14     for this work to compensate the contractor for these extended payment        part of your adjustment factor for JOC work and built into all other cost such as Labor Cost 
                                       January)           terms?                                                                       Factor, Firm Fixed Price cost, etc.  
                                                          Please provide pricing examples to illustratate 7% PBC calculation and       If the invoice is for a total of $1M, $70,000 will be put into the PBC Pool.  If the PBC is awarded 
           4        Jacobs      RFP Kick-off/Wrap-up      award based on 70% cumulative KPI score for each type of work:  Fixed        at 70% you would get $49,000. this applies regardless of the type of work.  
                                       Meeting            Price, Cost Plus, and JOC.
                                                          Exhibits J and K were issued on CD at the Pre-Proposal Conference. 
                                                          Please confirm that Exhibits J.1 through J.6 replace Exhibit O, and that 
                               FM Agreement – cover  Exhibit J.7 replaces the original Exhibit J.  Also, please confirm that 
           5        Turner              sheet             Exhibits K.1 through K.13 replace Exhibit P. 
                                                                                                                                       Yes.  Exhibit O in the RFP was released at the Pre-Proposal Kick Off meeting on the CD and 
                                                                                                                                       were labeled Exhibits J through J.6. The CD labeled Exhibit J7 replaces the RFP Exhibit J. The 
                                                                                                                                       CD labeled Exhibit K though K.13 replaces the RFP Exhibit P.
                                                          Exhibits L.1 through L.4 were issued on CD at the Pre-Proposal               Yes. Exhibit L in the RFP is Contractor Staffing. Exhibits L.1 through L.4 will receive alternative 
                                                          Conference. Please confirm that these Exhibits DO NOT replace the            labeling.
                               FM Agreement – cover  original Exhibit L (Contractor Staffing), and that the Exhibits L.1 through 
           6        Turner              sheet             L.4 should be titled Exhibits Q.1 through Q.4 (or some other letter).
                                                          It states “when AOC assigns”. On work generated and submitted by the         Most work under $15K will be done under the Facility Service Contract and most over $15K 
                                                          SP do they  assign our own generated work projects as JOC or Facilities      will be done as JOC.  There will be some expectations to this but this is the 95% rule.  All 
                                                          Service Contract?                                                            Contractor generated work will either fall into the Firm Fixed Price model or will have to be 
           7        Aleut      RFP – 1.5 Dual Contracts                                                                                approved by the AOC.  The AOC will at that time determine the manner in which the work will 
                                                                                                                                       be done.
                                                          What are the required quailifications for the "Regional BAS                  Section 2.2.1 of the Draft - BAS Policy Manual Rev. 0.6 12.15.10 requires that the BAS 
           8        Jacobs     BAS Policy, Section 2.2.1  Administrator"?
                                                                                                                                       Administrator be LONMark or BACNET certified.
                                                          What are the required quailifications for the "O&M Service Provider          The skills necessary to provide this support align with the Facility Plant Engineering function 
           9        Jacobs     BAS Policy, Section 2.2.1  Engineering"?
                                                                                                                                       within the RFP.  See Exhibit K Section 8
                                                          What are the required quailifications for the "IS Senior Technical Analyst"? This is an AOC staffed position.
          10        Jacobs     BAS Policy, Section 2.2.1
                                                                                                                          1
                                                                                                                    Response to RFP Questions
                                                             What are the required quailifications for the "Independent                        This is an AOC managed contractor.
           11        Jacobs      BAS Policy, Section 2.2.1   LONMark/BACNET Certified Third Party Company"?
                                                             What are the required quailifications for the "IS Applications Support            This is an AOC staffed position.
           12        Jacobs      BAS Policy, Section 2.2.1   Analyst"?
                                                             Please provide updated regional org chart to include required personnel           The current Regional Org chart within the RFP allows for sufficient Engineering and leadership 
           13        Jacobs      BAS Policy, Section 2.2.1   from BAS Policy Manual.
                                                                                                                                               skills to fulfill this requirement.
                                                             As related to the capability / willingness of Proposers to fulfill all of the     Yes, but we will only have contact with the Prime.  The Contractor can subcontract provided 
                                                             obligations in the Facilities Services Contract AND the JOC Contract, this        they retain control and responsibility, and their plan meets all the requirements of the 
                                                             section states that “Proposer may provide the Work and services either            contracts relating to subcontracting.  It is the AOC's intent to deal with one Prime Contactor.
                                                             through its own efforts or by utilizing subcontractors…”  Will the AOC 
                                                             allow for turnkey subcontracting of the entire obligation under one of the 
                                                             two Contracts?  Specifically, if a Proposer is feels that its strength is in JOC 
           14         ABM           RFP Section 3.1.2        Contracting, would that Proposer be permitted to subcontract 100% of 
                                                             the obligations in the Facilities Services Contract on a turnkey basis (and 
                                                             vice-versa)?
                                                             Will the AOC allow two Proposers (one with core strength and capability           Yes, but we will only have a contract with one Prime.  If you are proposing a formal Joint 
                                                             in Facilities Services Contracting, and the other with core strength and          Venture approach this would be accepted provided all other contract requirements are met.
                                                             capability in JOC Contracting) to partner together in a single response?
           15         ABM           RFP Section 3.1.2
                                                             If the AOC will allow two Proposers (one with core strength and capability  No
                                                             in Facilities Services Contracting, and the other with core strength and 
                                                             capability in JOC Contracting) to partner together in a single response, 
                                                             will the AOC entertain the concept of contracting with the two members 
           16         ABM           RFP Section 3.1.2        of the partnership separately (one contract with one of the partners for 
                                                             Facilities Services, and a separate contract with the other partner for 
                                                             JOC)?
                                                             Which buildings require chief engineers and Certified Building Technicians 
                                                             as stated: "The Regional Service Provider will provide the following 
                                                             minimum trained and certified staff per 1,000,000 square feet of space 
                                                             controlled by BAS systems: Chief Engineer – 2, Building Technicians ‐ 5"?         This standard represents an estimation of skills sets the qualified contractors will have to 
           17        Jacobs      BAS Policy, Section 3.3.2
                                                                                                                                               provide in order to meet the standard for ongoing system management. The AOC is actively 
                                                                                                                                               improving building control systems across the state and staff training and qualification will 
                                                                                                                                               need to align as portfolio growth occurs. A comprehensive list is not currently available. 
                                                                                                                                               Review of Exhibit L.4 and Exhibit J.4 may provide some limited information.
                                                             Should the cost of BAS personnel testing be included in phase-in?
           18        Jacobs      BAS Policy, Section 3.4.1                                                                                     Testing is seen as the validation process of a proper training program. Training shall comply 
                                                                                                                                               with RFP Section 5.3. Pricing for training should be incorporated into proposal costs in 
                                                                                                                                               compliance with RFP Section 11.6.
                                                             How will the BAS system be operated prior to building technicians being 
           19        Jacobs      BAS Policy, Section3.4.1    certified on BAS?
                                                                                                                                               The Service Provider is reponsible for providing this solution. 
                                                             How will training provided by the BAS Regional Support Group be funded?
           20        Jacobs      BAS Policy, Section 3.4.5
                                                                                                                                               Training is incorporated into the Firm Fixed Pricing of the contract.
                                                             For which buildings can the AOC provide "Building Schedule" to the SP?            A comprehensive listing is not available. See Section 3.5.1.1 of the Draft - BAS Policy Manual 
           21        Jacobs       BAS Policy, Section 3.7
                                                                                                                                               Rev. 0.6 12.15.10.
                                                             What is the AOC expectation for buildings that don't have a "Building 
           22        Jacobs       BAS Policy, Section 3.7    Schedule"?
                                                                                                                                               See Section 3.5.1.1 of the Draft - BAS Policy Manual Rev. 0.6 12.15.10.
                                                                                                                                  2
                                                                                                             Response to RFP Questions
                                                          For which buildings can the AOC provide "Building Setpoints" to the SP?
           23       Jacobs      BAS Policy, Section 3.7
                                                                                                                                        See Section 3.5.1.2 of the Draft - BAS Policy Manual Rev. 0.6 12.15.10.
                                                          What is the AOC expectation for buildings that don't have "Building 
           24       Jacobs      BAS Policy, Section 3.7   Setpoints"?
                                                                                                                                        See Section 3.5.1.2 of the Draft - BAS Policy Manual Rev. 0.6 12.15.10.
                                                          For which buildings can the AOC provide "Sequence of Operations" to the  A comprehensive listing is not available. See Section 3.7of the Draft - BAS Policy Manual Rev. 
           25       Jacobs      BAS Policy, Section 3.7   SP?
                                                                                                                                        0.6 12.15.10.
                                                          What is the AOC expectation for buildings that don't have "Sequence of 
           26       Jacobs      BAS Policy, Section 3.7   Operations"?
                                                                                                                                        See Section 3.7of the Draft - BAS Policy Manual Rev. 0.6 12.15.10.
                                                          For which buildings can the AOC provide "Facility Manual Operation            A comprehensive listing is not available. See Section 3.7of the Draft - BAS Policy Manual Rev. 
           27       Jacobs      BAS Policy, Section 3.7   Process" to the SP?
                                                                                                                                        0.6 12.15.10.
                                                          What is the AOC expectation for buildings that don't have a "Facility 
           28       Jacobs      BAS Policy, Section 3.7   Manual Operation Process"?
                                                                                                                                        See Section 3.7of the Draft - BAS Policy Manual Rev. 0.6 12.15.10.
                                                          For which buildings can the AOC provide "Emergency Management                 A comprehensive listing is not available. See Section 3.7of the Draft - BAS Policy Manual Rev. 
           29       Jacobs      BAS Policy, Section 3.7   Protocol" to the SP?
                                                                                                                                        0.6 12.15.10.
                                                          What is the AOC expectation for buildings that don't have an "Emergency 
           30       Jacobs      BAS Policy, Section 3.7   Management Protocol"?
                                                                                                                                        See Section 3.7of the Draft - BAS Policy Manual Rev. 0.6 12.15.10.
                                                          For which buildings can the AOC provide "BAS Drawings" to the SP?             A comprehensive listing is not available. See Section 3.7of the Draft - BAS Policy Manual Rev. 
           31       Jacobs      BAS Policy, Section 3.7
                                                                                                                                        0.6 12.15.10.
                                                          What is the AOC expectation for buildings that don't have "BAS 
           32       Jacobs      BAS Policy, Section 3.7   Drawings"?
                                                                                                                                        See Section 3.7of the Draft - BAS Policy Manual Rev. 0.6 12.15.10.
                                                          For which buildings can the AOC provide "Variance Report" to the SP?          A comprehensive listing is not available. See Section 3.7of the Draft - BAS Policy Manual Rev. 
           33       Jacobs      BAS Policy, Section 3.7
                                                                                                                                        0.6 12.15.10.
                                                          What is the AOC expectation for buildings that don't have a "Variance 
           34       Jacobs      BAS Policy, Section 3.7   Report"?
                                                                                                                                        See Section 3.7of the Draft - BAS Policy Manual Rev. 0.6 12.15.10.
                                                          For which buildings can the AOC provide "AOC compliant Refrigerant            Refrigerant Management Plans are in the process of being finalized for all facilities that contain 
           35       Jacobs      BAS Policy, Section 3.7   Management Plan" to the SP?
                                                                                                                                        code required plans.
                                                          What is the AOC expectation for buildings that don't have an "AOC             See RFP Section 2.7.10 Refrigerant Management Plan
           36       Jacobs      BAS Policy, Section 3.7   compliant Refrigerant Management Plan"?
                                                          For which buildings can the AOC provide "AOC based Preventive                 This document was provided on the CD at the Pre-Proposal Kick Off Meeting and is labeled 
           37       Jacobs      BAS Policy, Section 3.7   Maintenance Schedule" to the SP?                                              Exhibits J.5
                                                          What is the AOC expectation for buildings that don't have an "AOC based  See Exhibit B Section 1.1
           38       Jacobs      BAS Policy, Section 3.7   Preventive Maintenance Schedule"?
                                                          For which buildings can the AOC provide "Mechanical Zone                      A comprehensive listing is not available. See Section 3.7of the Draft - BAS Policy Manual Rev. 
           39       Jacobs      BAS Policy, Section 3.7   Locations/Mapping" to the SP?
                                                                                                                                        0.6 12.15.10.
                                                          What is the AOC expectation for buildings that don't have "Mechanical 
           40       Jacobs      BAS Policy, Section 3.7   Zone Locations/Mapping"?
                                                                                                                                        See Section 3.7of the Draft - BAS Policy Manual Rev. 0.6 12.15.10.
                                                          For which buildings can the AOC provide "Access Codes and Passwords"          A comprehensive listing is not available. See Section 3.7of the Draft - BAS Policy Manual Rev. 
           41       Jacobs      BAS Policy, Section 3.7   to the SP?
                                                                                                                                        0.6 12.15.10.
                                                          What is the AOC expectation for buildings that don't have "Access Codes 
           42       Jacobs      BAS Policy, Section 3.7   and Passwords"?
                                                                                                                                        See Section 3.7of the Draft - BAS Policy Manual Rev. 0.6 12.15.10.
                                                          For which buildings can the AOC provide "Point ID & Controller ID             A comprehensive listing is not available. See Section 3.7of the Draft - BAS Policy Manual Rev. 
           43       Jacobs      BAS Policy, Section 3.7   information" to the SP?
                                                                                                                                        0.6 12.15.10.
                                                          What is the AOC expectation for buildings that don't have "Point ID & 
           44       Jacobs      BAS Policy, Section 3.7   Controller ID information"?
                                                                                                                                        See Section 3.7of the Draft - BAS Policy Manual Rev. 0.6 12.15.10.
                                                          For which buildings can the AOC provide "Current Re‐boot/Restore Disk"  A comprehensive listing is not available. See Section 3.7of the Draft - BAS Policy Manual Rev. 
           45       Jacobs      BAS Policy, Section 3.7   to the SP?
                                                                                                                                        0.6 12.15.10.
                                                                                                                           3
                                                                                                             Response to RFP Questions
                                                          What is the AOC expectation for buildings that don't have a "Current Re‐
           46       Jacobs      BAS Policy, Section 3.7   boot/Restore Disk"?
                                                                                                                                        See Section 3.7of the Draft - BAS Policy Manual Rev. 0.6 12.15.10.
                                                          What documents are considered "Reference Documents"?
           47       Jacobs      BAS Policy, Section 3.7                                                                                 Operations and Maintenance Manuals, Training Guides, Warranty Documents, Service 
                                                                                                                                        Protocols, and any other document appropriate for inclusion into the Systems Manual.
                                                          Section cited states that “…Contractor will provide escort…for any            The plan is for a 90 day transition which will allow time for clearance processing.  The AOC will 
                                                          Contractor or subcontractor employees…”   Please explain how this will        work with the contractors during the transition period to find a cooperative solution.  
                                                          be accomplished during the transition and early phases of the contract; 
           48        CBRE         5.2 (RFP page 10)       that is, before the incoming contractor has completed clearance 
                                                          processing for
           49        CBRE         5.8 (RFP page 11)       Please define the term “SWO” and how it applies.                              See Exhibit A Page 6.
                                                          For late payments, other than what's listed in this section, can              There will be no specific line item for this.  It is anticipated that it will be part of your 
                                                          finance/interest be charged?  If yes, at what rate?  If no, what has been     adjustment factor for JOC work and built into all other cost such as Labor Cost Factor, Firm 
                                                          AOC's historical payment cycle from the date the invoice is submmited         Fixed Price cost, etc.  Payment cycle will vary but plan on roughly 60 days from the time of 
           50       Jacobs         FSC Section 7.10       until it is paid?  And what is the average monthly invoice amount for each  invoice.  Some payments will occur sooner some will be slightly longer.
                                                          region:  BANCRO, NCRO, SRO?
                                                          Have there been delays in the past, due to State Budget issues?  If yes,      Ye,  but most payments are made with-in 60 days.  Specific data is not readily available.  
           51       Jacobs         FSC Section 7.11       what has been the average time from invoice approved to issuance of 
                                                          warrants for the past 5 years?
                                                          Please explain the last sentence of this section, which states “…             This means that the list includes some, but not all, of the criteria that will be used in the 
           52        CBRE          10.1 (RFP Page 14)     information in this sections is…not an exhaustive list of the requirements  evaluation.  
                                                          and procedures for the award of contracts.”
                                                          Is there any preference between government and commercial                     No preference, provided you can show the type of work being requested is similar to the work 
           53        CBRE       10.1.1.4 (RFP page 15)    references?  Or are references from both public and private enterprise        done on the referenced contracts. 
                                                          clients requested?
                                                            Is the single separate introduction letter also bound into the document  It should be in the bound document and does not count toward page count.
           54       Jacobs        RFP, Section 11.1.1       as well as a stand alone? If so, is it part of the 12-page count for section 
                                                            11.1?
                               RFP, Section 11.1.1 and      Do you need Proposer information in both places?                            Yes, but we see these as two different questions.
           55       Jacobs               11.2
                               RFP, Section 11.1.4 and      Do you need our project history in both places?                             Yes, you can reference between the two.
           56       Jacobs              11.3.3
                                                          Will AOC accept contracts outside of the State of California for experience  Yes.
                               11.3.4 Experience in Job  in this section?
                                 Order Contracting or 
           57        Pride            Indefinite 
                                  Delivery/Indefinite 
                                  Quantity Contracts
           58        Aleut           11.4 Staffing        Who are the key staff and how are they identified?                            See Exhibit L of the Facility Service Contract.
                                                            Additional page per position, is that per region (if more than one region Yes, if the same person or job description is used for all regions proposed there is no need to 
           59       Jacobs        RFP, Section 11.4.4       is proposed)?                                                               duplicate the same information two or three times.
                                                          Is the Phase-In Cost subject to the 7% Performance Based Compensation  No
           60       Turner            RFP 11.6.7          Pool?
                                                          Is the Phase-Out Cost subject to the 7% Performance Based                     No
           61       Turner            RFP 11.6.7          Compensation Pool?
                                                                                                                           4
The words contained in this file might help you see if this file matches what you are looking for:

...Response to rfp questions question company solicitation reference number can you please post the signin sheets from site visits gerald list of companies have completed all pre proposal meeting and tour requirements kitchell mentioned they would be made available thank further participate in this was uploaded aoc website on january during wrap up session immediately following tours stated that contractors should received a computer disk containing cds referenced were provided per at preventive maintenance workorder data our firm never cbre friday such how do we obtain one preproposal kick off th there set totaling with exhibits labeled exhibit jj kk ll document draft bas policy manual three relevant joc contracting documents for ncro bancro sro closing informed may some misunderstanding payments projects under k will final payment idiq or task order work only invoiced month project is could same it started reimbursed semiannual basis progress told several months afterwards days after re...