                                                                 Ref. No.: MHHE/ITB/SCM/11-REV0
                                                   
                                                                              CONTRACT
                                                                               EXHIBIT 6
                                                                             Page 1 of 11
         ___________________________________________________________________________________________________________________
                              SUPPLIER DOCUMENT INSTRUCTIONS
                                      TABLE OF CONTENT
         ITEM                 SUBJECT                                      PAGE
         1.0              PURPOSE                                            2
         2.0              REFERENCE DOCUMENTS                                2
         3.0              DEFINITIONS                                        2
         4.0              COMMUNICATION ADDRESS AND FACSMILE                 2
         5.0              MEETINGS                                           3
         6.0              REPORTING                                          3
         7.0              DRAWING AND DOCUMENT SUBMISSION PROCEDURES 4
         8.0              EQUIPMENT VENDOR MANUALS                           7
         9.0              PAYMENT AND INVOICING                              7
         10.0             WAREHOUSE OPERATING FOR RECEIVING                  8
         11.0             VARIATION ORDER                                    9
         12.0             SUPPLIER DOCUMENT REQUIRED LIST (SDRL)             9
         13.0             CONTRACT CLOSURE                                   9
         APPENDIX 5       SAMPLE OF CUSTOMER PROGRESS REPORT
         APPENDIX 6       ONLINE CERTIFICATE PROGRESS CLAIM (CPC) 
                          SUBMISSION MATERIAL PURCHASES (MILESTONE PAYMENT)
         APPENDIX 7       ONLINE INVOICE SUBMISSION
         APPENDIX 8       SPARE PARTS INTERCHANGEABLE RECORDS (SPIR)
         APPENDIX 9       VARIATION ORDER PROPOSAL FORMS (VOPF)
         APPENDIX 10      FORMAT FOR CONTRACT CLOSURE LETTER
         APPENDIX 11      FORMAT FOR CONTRACT CLOSURE CERTIFICATE
         APPENDIX 12      SUPPLIER DOCUMENT REQUIREMENTS LISTING (SDRL) 
         1.0   PURPOSE
               The purpose of this guideline is to describe the required method of CONTRACT
               implementation   between   MMHE and SUPPLIER with respect to documentation
               submissions specified in CONTRACT. All costs for the fulfilment of the requirements of
               this Exhibit 6: Supplier Document Instructions shall be included in Exhibit 5: Schedule
               of Compensation.
                                                                                                     Ref. No.: MHHE/ITB/SCM/11-REV0
                                                       
                                                                                                                        CONTRACT
                                                                                                                          EXHIBIT 6
                                                                                                                       Page 2 of 11
             ___________________________________________________________________________________________________________________
             2.0       REFERENCE DOCUMENTS
                       This section must be read together with the PURCHASE ORDER and Exhibit 4: Scope
                       of Supply.  
             3.0       DEFINITIONS
                       MMHE  – Malaysia Marine and Heavy Engineering Sdn Bhd who will issue the
                       CONTRACT. 
                       SUPPLIER - any person or company to whom the CONTRACT/PURCHASE ORDER is
                       issued for the supply of WORK. 
             4.0       COMMUNICATION ADDRESSES AND FACSIMILE
                       Any notices and communications required to be given under this CONTRACT shall be
                       in writing.  Such notices and communication shall be deemed to be duly given when
                       they shall have been delivered by hand, E-mail, or facsimile, to the parties to which
                       they are required to be given such party’s address as specified following:
                       4.1      Malaysia Marine and Heavy Engineering Sdn. Bhd.
                                MMHE Representative                  : 
                                Address                              :
                                Telephone                            :
                                Telefax                    :
                                E-mail Address                       :
                                SITE Representative                  : 
                                Address                              :
                                Telephone                            :
                                Telefax                    :
                                E-mail Address                       :
                       4.2      
                                SUPPLIER Representative              : 
                                Address                              :
                                Telephone                            :
                                Telefax                    :
                                E-mail Address                       :
                                PROJECT Representative               : 
                                Address                              :
                                Telephone                            :
                                Telefax                    :
                                E-mail Address                       :
             5.0     MEETINGS
                     5.1.       The SUPPLIER shall hold meetings on the dates set by MMHE and in
                                accordance with the CONTRACT, and additionally, as often as is necessary
                                for keeping all parties fully informed with respect to the progress of the
                                WORK and for discussing technical subjects and resolving such problems
                                as may arise in the execution of the WORK. MMHE shall  advise the
                                                               Ref. No.: MHHE/ITB/SCM/11-REV0
                                                   
                                                                           CONTRACT
                                                                            EXHIBIT 6
                                                                           Page 3 of 11
         ___________________________________________________________________________________________________________________
                    scheduling of meetings in writing.
              5.2.  All meetings scheduled throughout the performance of the CONTRACT
                    shall be minuted by MMHE and the minutes of each meeting shall be issued
                    to the SUPPLIER within 2 working days.
              5.3.  When resolution of issues is not possible within the meeting, or where the
                    matter requires some action on the part of the SUPPLIER or MMHE, then
                    this shall be indicated in the minutes, and MMHE or the SUPPLIER shall
                    subsequently respond in writing providing the necessary information and/or
                    confirming the course of action, as appropriate.
              5.4.  The SUPPLIER shall advise MMHE by giving two (2) days written notice of
                    all meetings of a technical nature to be held between the SUPPLIER and its
                    SUBSUPPLIERS. MMHE reserves the right to attend all such meetings in
                    order to ensure that the WORK  is completed in accordance with the
                    CONTRACT. Attendance by MMHE shall in no way relieve the SUPPLIER of
                    any of its responsibilities as set forth in the CONTRACT.
              5.5.  In general, all meetings after the EFFECTIVE DATE shall be conducted at
                    MMHE'S SITE Office. However, there may be a requirement for monthly
                    management   meetings   between   MMHE   REPRESENTATIVE   and   the
                    SUPPLIER REPRESENTATIVE, which may be held at MMHE'S office in
                    Kuala Lumpur and/or Pasir Gudang Yard. 
         6.0   REPORTING
         6.1.       General
                    The SUPPLIER shall keep MMHE fully informed on all aspects of the WORK
                    that affect progress. The SUPPLIER shall provide the following reports as
                    required by the CONTRACT:
                    6.1.1. Weekly Progress Report (Refer to Exhibit 6 – Appendix 5: Sample of
                          Customer Progress Report).
                    6.1.2. Ad-hoc reports: any reports required due to unforeseen circumstances.
                    6.1.3. All reports shall be addressed to MMHE REPRESENTATIVE.
                    6.1.4. All reports shall be in standard ISO A4 size.
         6.2.       Weekly Progress Report
                     6.2.1. Throughout the performance of the WORK, the SUPPLIER shall
                           prepare and submit a Weekly Progress Report to MMHE within two
                           (2) days of the weekly cut-off date.
                     6.2.2. The Weekly Progress Report shall be in narrative, tabulation and
                                                                                       Ref. No.: MHHE/ITB/SCM/11-REV0
                                                      
                                                                                                        CONTRACT
                                                                                                         EXHIBIT 6
                                                                                                       Page 4 of 11
            ___________________________________________________________________________________________________________________
                                    graphical form and shall report on the following aspects of the WORK:
                                    (a)    Progress narrative covering all areas of operation.
                                    (b)    Areas of concern, including impact and proposed mitigation
                                          measures.
                                    (c)    Schedule bar chart including  all   activities   within   the   logic
                                          network, showing planned and actual starts and finishes, sorted
                                          by WBS and scheduled start in a format agreed with MMHE.
                                    (d)    Progress S-curve showing planned, actual and forecast progress
                                          for each of the major elements of the WORK, down to Level 2.
                                    (e)    A summary procurement tabulation for requisitions and purchase
                                          orders detailing total identified and status of enquiry and award
                                          activities.
                                    (f)    Project photographs both in hard and soft copy.
                    6.3Materials Report
                            The Materials Report section shall include, as a minimum, the following
                            information:
                                    (a)   A material progress and tracking report for all materials to be
                                          supplied by the SUPPLIER and MMHE (separately) giving
                                          details of the requisition or order number, the description of
                                          the material, the quantities ordered, the quantities required to
                                          complete the WORK, the quantities ordered for spare, the date
                                          ordered, the supplier, the date due or actually delivered and
                                          the certificate or inspection report number.
                                    (b)   The Materials Report shall also include the planned and actual
                                          progress of manufacturing and the planned and forecast
                                          delivery dates.
                   6.4       Final Report
                            6.4.1 The   Final   Report   as   per   SDRL   in   the   Approved   for   Purchase
                                    Specification.
            7.0     DRAWING AND DOCUMENT SUBMISSION PROCEDURES
                    7.1.   All drawings and required documents shall be submitted via uploading the file in
                           MMHE online Vendor Data Management System (VDMS).
                    7.2.   Drawings
The words contained in this file might help you see if this file matches what you are looking for:

...Ref no mhhe itb scm rev contract exhibit page of supplier document instructions table content item subject purpose reference documents definitions communication address and facsmile meetings reporting drawing submission procedures equipment vendor manuals payment invoicing warehouse operating for receiving variation order required list sdrl closure appendix sample customer progress report online certificate claim cpc material purchases milestone invoice spare parts interchangeable records spir proposal forms vopf format letter requirements listing the this guideline is to describe method implementation between mmhe with respect documentation submissions specified in all costs fulfilment shall be included schedule compensation section must read together purchase scope supply malaysia marine heavy engineering sdn bhd who will issue any person or company whom issued work addresses facsimile notices communications given under writing such deemed duly when they have been delivered by hand e...

no reviews yet
Please Login to review.