380x Filetype PPTX File size 1.95 MB Source: www.konkurentsiamet.ee
PRODUCT STRUCTURE
SNAPSHOT
Capacity product booking is organized via auctions (except for stock transfer
product and virtual counterflow product)
Product tariff is approved by the regulator. The auctions are for premium fee for
receiving guaranteed storage service. Auction price mechanism is Pay-as-Cleared.
Congestion management forsees that constant capacity takes priority over
interruptable capacity. Until D-1 15:00 allocations ar made pro rata; after first
come first served.
2 BCP/ BCP/ GJP ICP/ AJP STP/KPP
2GJP Constant capacity Interruptible capacity Stock transfer product
product product
Risk hedging product Available in low demand
Limited to 2 Limited to available Volume determined on
TWh/cycle to ensure capacity. Tariff set to storage cycles. Tariff set 2nd of May. Tariff set to
best technical be equal to unit below unit costs taking promote efficient use of
capacity of the costs. into account risks the storage by ensuring
storage. Tariff set related to insufficient STP costs more than
taking into account use of storage. 2GJP (with premium) for
hedging advantages the respective cycle.
PRODUCT
TARIFFS
TARIFF
2 BCP 2TWh x 2 Years ,
K ≥1
constant 2GJP
BCP
constant [Forecasted
capacity] – [2BCP]
ICP TWh
0.4 1
interruptibl (for tariff project) KPP
e
INJECTION SEASON
SCHEDULE
TARIFF 2BCP BCP TARIFF CAPACITY
SETTING 1ST AUCTION 1ST AUCTION PERIOD STARTS PUBLICATION
UNTIL END OF NO LATER THAN NO LATER THAN 1ST OF MAY NO LATER THAN
FEB 15TH OF MAR 15TH OF MAR 21ST OF MAY
(EXPECTED)
2BCP+BCP ICP* ICP* ICP* INJECTION
2ND AUCTION JUN AUCTION JUL AUCTION AUG AUCTION SEASON ENDS
2 B-DAYS AFTER NO LATER THAN NO LATER THAN NO LATER THAN 15TH OF OCT
CAPACITY 1ST & 15TH 1ST & 15TH 1ST & 15TH
PUBLICATION OF JUN OF JUL OF AUG
* If there is available capacity
Thank you
for
attention!
Contact:
P: +371 67 097 200
E: sprk@sprk.gov.lv
W: sprk.gov.lv