171x Filetype PDF File size 0.44 MB Source: www.eversheds-sutherland.com
14 fidic FIDIC Yellow Book and judicial interpretation James Pickavance and Kate Sanger of Eversheds analyse a recent court ruling interpreting the FIDIC Yellow Book with implications for both employers and contractors. tion at the Gibraltar Airport. These works comprised the design and construction of a road and tunnel under the KEY POINTS eastern end of the runaway (works). Following some pre- l A ‘common sense’ approach will be applied by liminary site investigations, GOG issued an invitation to the courts to the resolution of disputes where tender to a number of potential tenderers for the works. the parties have contracted on a FIDIC basis Ultimately it signed an agreement with OHL in No- l Sub-cl 4.12 (unforeseen physical conditions) vember 2008, which was based on a largely unamended imposes an active responsibility on the FIDIC Yellow Book. The construction period was two contractor to have appropriate regard to, years, but progress of the works was significantly delayed and to interpret, site data and pre-contract information, and to price bids accordingly and, after 30 months, approximately only 25% of the l Sub-cl 20.1 (contractors’ claims) will be works were completed. construed broadly. The wording of the On 16 May 2011 a notice to correct was sent to clause means that contractors could submit OHL pursuant to sub-cl 15.1 (initial notice to correct). a claim for either a prospective delay or a It set out a number of alleged breaches of contract (a retrospective delay number of which were premised on sub-cl 8.1 (failure l An employer exercising its rights to to proceed with due expedition and without delay)); the terminate for contractor default under sub- cl 15 (termination) must do so only where remediation steps to be taken in respect of each breach; the breach giving rise to the termination is and the time by which the breaches were to be remedied. substantial, but a substantial breach did not OHL was warned that failure to achieve any one of itself need to amount to repudiatory conduct the required remedial actions in the notice to correct would entitle GOG to terminate the contract. OHL denied liability, claiming that unforeseen levels of soil contamination were to blame, the risk for which lay with GOG. A second notice to correct was issued pursuant to sub-cl 15.1 on 5 July 2011 (second notice). he recent decision of Obrascon Huarte Lain SA This second notice to correct related specifically to the v A-G for Gibraltar [2014] EWHC 1028 (TCC) failure to commence excavation work as instructed. Thas provided some valuable insight as to the court’s On 28 July 2011 GOG sent a notice of interpretation of three key provisions of the FIDIC termination pursuant to cl 15.2 of the contract, Conditions of Contract for Plant and Design-Build (1st notifying that the contract would be terminated on edn, 1999) (FIDIC Yellow Book). In this case, proceed- 12 August 2011 as a result of OHL’s failure to comply ings were brought by Obrascon Huarte Lain SA (OHL) with the notices to correct (sub-cl 15.2(a)); and/or against the Government of Gibraltar (GOG) in relation demonstration of an intention not to continue the to GOG’s termination of a construction contract. GOG performance of its obligations under the contract decided to undertake works to resolve the traffic conges- (sub-cl 15.2(b)); and/or failure, without reasonable fidic 15 excuse, to proceed with the works in accordance with risk: (i) Make a substantial financial allowance within cl 8 of the contract (sub-cl 15.2(c)). the tendered price for this. (ii) Plan and price for a OHL responded on 3 August 2011, advising GOG post-contract site investigation accordingly. (iii) Plan to that it considered the notice of termination wrongful remove all the made ground which could be assessed as and amounted to a repudiatory breach of contract. having a good chance of containing contaminants. (iv) On 20 August 2011, GOG informed OHL that it Plan the design and construction of the works on the was terminating the contract, alternatively accepting a basis that there was an unacceptable risk of significant repudiation on the part of OHL (for various reasons). quantities of contaminants randomly distributed in the Akenhead J held that OHL’s breaches of contract had ground (which it was noted was what OHL’s belated been sufficient to justify a termination under cl 15, and redesign had sough to achieve). the contract had been lawfully terminated. In arriving at this decision, three key provisions of the FIDIC Yellow Contractors’ claims Book – unforeseeable physical conditions., notice of A contractor’s entitlement to an extension of time claim and termination – were examined in detail. pursuant to sub-cl 8.4 is subject to sub-cl 20.1 (contractors’ claims). In assessing OHL’s claims for Unforeseen physical conditions extension of time, Akenhead J noted: OHL claimed that the amount, location and extent of l The service of a notice by a contractor required by contamination in the ground, contamination in the sub-cl 20.1 as soon as practicable, and not later than water and rock excavation, were physical conditions 28 days after the contractor became aware, or should that were not reasonably foreseeable by an experienced have become aware, of the event or circumstance is a contractor by the date of submission of its tender. precondition to an award of additional time and/or OHL argued that, pursuant to sub-cl 4.12, this cost under the contract. unforeseeability entitled it to an extension of time for l Irrespective of this precondition, the clause was to be completion under sub-cl 8.4. construed broadly, and not interpreted strictly against This argument was not successful. Akenhead J the contractor. held, on the facts, that the quantities of contaminated l The wording ‘event or circumstance’ in sub-cl 20.1 materials in the ground were in fact likely to have been therefore meant that contractors could submit a claim less than could have reasonably been foreseen by an for an extension of time either when it is clear that experienced contractor. Akenhead J noted: there will be a delay (prospective) or when the delay l Sub-clause 4.12 imposed a positive obligation on has at least started to be incurred (retrospective). a contractor to have appropriate regard to, and to l The onus of proof was on the employer to prove interpret, site data and pre-contract information and that the notice required by sub-cl 20.1 was to price bids accordingly. submitted outside the 28-day-period. l It was not reasonable for OHL to rely on preliminary l Sub-clause 20.1 did not specify any form of information provided in an invitation to tender. An notice, besides that service must be recognisable experienced contractor would not limit itself to an as a ‘claim’. OHL’s reliance on monthly weather analysis of the geotechnical information contained in progress reports as evidence of a claim under sub- a pre-contract site investigation report. cl 20.1 was insufficient. l A contractor provided with preliminary information regarding site contamination was obliged to carry out Clause 15 (termination) some intelligent assessment and analysis of: (i) why GOG terminated on three separate grounds; sub-cll the site was contaminated; and (ii) what the real risk 15.2(a), 15.2(c) and 15.2(b). was of encountering more contaminated material than envisaged at tender stage. Sub-clause 15.2(a) – notices to correct l Where there is foreseeable uncertainty of the precise The notices to correct issued by GOG identified a type, location and quantity of contaminated soil, number of contractual breaches, the remediation steps to bidding contractors could reasonably have taken some be taken in respect of those breaches, and a time by which or all of the following steps pre-contract to address this the breaches were to be remedied. Where an employer December 2014 16 fidic seeks to terminate a contract pursuant to sub-cl 15.2(a) a failure to ‘proceed with the Works in accordance with for failure to comply with a notice to correct under sub-cl Clause 8’. In a fairly scathing assessment of OHL’s 15.1, the notice issued pursuant to sub-cl 15.1 will itself performance, Akenhead J stated that he was satisfied be examined in order to determine whether or not the that OHL had failed to proceed in accordance with termination is justified. Akenhead J noted: cl 8.1, meaning that OHL was in default under cl 8.1 l The primary purpose of sub-cl 15.1 is to give a already on 28 July 2011. Although there were some contractor the right of remedy. expressions by OHL wanting to proceed with the works, l Accordingly, for an employer to issue a notice its inactivity indicated otherwise. under sub-cl 15.1: (i) there must be a significant or substantial failure. However, a substantial failure did Significance not itself need to amount to repudiatory conduct; This decision will be relevant to both employers and and (ii) the failure must be established as a failure to contractors. To date, judicial guidance on FIDIC comply with the contract. provisions has been limited as disputes involving FIDIC l The time for making good specified by the employer contracts are usually resolved in arbitration. Whilst the in a notice issued under sub-cl 15.1 must be judgment was lengthy and detailed, and the case itself considered ‘reasonable’ in all of the circumstances was largely determined on its particular facts, prevailing at the time of the notice. Akenhead J’s comments on the provisions discussed l The fact that liquidated damages were payable for the above indicate that a ‘common sense’ approach will be failure to complete on time did not qualify the right applied to the resolution of disputes in circumstances to terminate under sub-cl 15.2 for failing to proceed where the parties have contracted on a FIDIC basis. with due expedition and without delay. Akenhead J’s decision regarding unforeseen physical conditions confirms both that the determination Sub-clause 15.2(b) of a claim under sub-cl 4.12 will require a detailed Akenhead J held that OHL had, on the facts, examination of the facts, and that contractors will be demonstrated an intention not to continue performance judged by an objective standard. in accordance with its obligations under the contract This decision indicates that courts are unlikely to so as to give rise to an entitlement to terminate. In be sympathetic to contractors who simply rely on considering the standard to be satisfied by sub-cl preliminary site information, submit a low offer and then 15.2(b), Akenhead J noted: seek additional relief by way of a claim for site conditions l Where an employer purports to terminate under following commencement of works. sub-cl 15.2(b) on the basis the contractor has Whilst employers will generally exercise a contractual either abandoned the works or otherwise plainly right to terminate only as a ‘last resort’, this decision demonstrated the intention not to continue indicates that courts will uphold an employer’s performance of its obligations under the contract, contractual right to terminate a contractor’s employment a verbal and contractual distinction needed to under sub-cl 15.2 in circumstances where the be drawn between an intention to continue termination can be justified. performance and an intention to continue Finally, it is probable that this ‘contractor-friendly’ performance of the contractual obligations. interpretation of sub-cl 20.1 will be relied upon by l Determining an intention not to continue performance contractors to reduce the risk of losing the entitlement could be judged by both words and actions. to an extension of time in circumstances where it has l Here a prolonged failure to perform in accordance arguably failed to provide notice. Similarly, employers with the contract, with no demonstrable intent to seeking to enforce the 28 day notice period for claims are remedy the failure or recommence the permanent likely to be more alert to ensuring drafting amendments works until a commercial solution was reached, are made to clarify that this is the intended position. ultimately justified termination. While Akenhead J’s analysis of sub-cl 20.1 was in this instance restricted to claims for extensions of time, the Sub-clause 15.2(c)(i) broad interpretation may well be relied on by contractors The majority of items in the first notice to correct alleged when submitting claims for additional costs. CL
no reviews yet
Please Login to review.