General Outline
Scope, Interfaces, and External Dependencies
Technical Status and Progress
Procurement Status and Progress
QA/QC
Approved BCRs
Schedule
Cost and Schedule Performance & VAR Reports
Estimate at Completion
Risks
ES&H
Summary
HL-LHC AUP IPR DOE/SC Review– Jan 14-16, 2019 2
Charge 1
WBS 302.4.01: Scope and Interfaces
From WBS Dictionary US-HiLumi-doc-39
Receive MQXFA magnet from
LBNL
Prepare magnet for test at 1.9K in
vertical test cryostat
Test magnet and analyze results
Ship magnet to FNAL (for assembly
into a cold mass) or to LBNL (for re-
build if test failed)
Deliverables: 22 magnet tests
WBS scope is clearly defined and well understood.
Interfaces are defined and controlled
HL-LHC AUP IPR DOE/SC Review– Jan 14-16, 2019 3
WBS 302.4.01: Scope and Interfaces
Magnets Vertical Test (302.4.01) is a component of the overall work flow
(US-HiLumi-doc-138) Vertical
Test Stand
Manufacturing Flow (BNL)
Coil Parts (FNAL)
Final Design
Final Design
Boxes with dashed lines
ICBA New ICBA New IB1 Test are not part of AUP
Building Building Stand
(FNAL) (FNAL) (FNAL)
Cryo - Cryo -
Assembly Assembly Test
HL-LHC AUP IPR DOE/SC Review– Jan 14-16, 2019 4
WBS 302.4.01: Scope and Interfaces
Interface Control Matrix is from:
US-HiLumi-doc-219
US-HiLumi-doc-1151
US-HiLumi-doc-321
US-HiLumi-doc-207
Interfaces are defined and controlled.
HL-LHC AUP IPR DOE/SC Review– Jan 14-16, 2019 5
WBS 302.4.01: Organization
US-HiLumi-doc-104
US HL-LHC Accelerator Upgrade Project: 302.4.01 Magnets Vertical Test
Experienced Team:
Joe Muratore
Piyush Joshi
Honghai Song
Andy Marone
Bill McKeon
Frank Teich
Sonny Dimaiuta
Dan Sullivan WBS 302.4.01 team in
John Cintorino place. There are clear roles
Pat Doutney and responsibilities
Pete Galioto
HL-LHC AUP IPR DOE/SC Review– Jan 14-16, 2019 6